Title Page

  • Tesco SAYS Handset Only Pre-Start

  • Document Revision :-

  • Conducted on

  • Prepared by

Surveyors Information

  • One arrival at the store please ensure that you sign in and out using the stores visitors book. Once signed in please ask to speak to the Store SAYS Champion or Duty Manager, Inform them that you are here to complete a survey for the installation of SAYS and will ask for them on completion to sit down and discuss the installation and any store concerns.

    To ascertain this information, please complete the below information with as much information as possible, where possible please take photos to help describe the areas identified.

General Summary of Project Roll-Out Scope of Works

  • Night 0 -

    ISG to install power/data cables to produce plinths, Scanner Wall, re-scan bench and pay stations ensuring a port is available for the installation of the server the following day by Zebra.


    Night 1 -

    ALS - Remove and relocate checkouts, relocate existing SSC & associated cash tube works. Relocation & installation of power/data poles, relocation IQM where applicable. Installation of new SAYS flooring, Scanner wall, re-scan bench, Scanner return holders, New Totem and Woodtech barrier rails. Installation of produce plinths and box infills where applicable to store plan, relocation of produce gondola where applicable, relocate and install hanging signage / POS.

    ISG - Decommissioning of power/data to all mainbank checkouts, baskets checkouts and SSC being removed or relocated, connect all power/data to produce plinths, mainbank checkouts, Express checkouts, SSC, Scanner Wall, and re-scan bench.
    All to be tested on completion

    Herbert's - AOIF works to checkouts and verify scales on relocated checkouts, carry-out modifications to countwise system.

    Gratte - Relocation and installation of CCTV Cameras

    NCR - Relocation and commissioning of till IT equipment and SSC payment lanes.

    Checkpoint - Relocation of EAS gate to Corel exit as per drawing.

    Zebra - Commissioning of Handsets and Scanner Wall


    ""TESCO SINGLE POINT OF CONTACT FOR STORE MANAGEMENT""
    FIRST POINT OF CALL FOR ANY PRE-INSTALLATIONS AND POST INSTALLATION
    QUERIES OR QUESTIONS IS
    Clement Bourcart - 07736 1205576 - clement.bourcart@uk.tesco.com

Survey Details

  • Primary Survey Date:

  • Surveyor Name:

  • Drawing ID

  • Survey Version Control & Revision Log

  • Amendment
  • Revision Changes

  • Person responsible for Amendment

  • Contractors in Attendance

  • Power/Data

  • Other

  • Other

  • Summary of Contractors Required for this installation (Information used by ALS for "RAMs")

Installation dates / times

  • Night 0 start on site date / time

  • Night 1 start on site date / time

  • Night 2 start on site date / time

  • SAYS Training data / time

  • SAYS Go Live date

General Store Information

  • Client

  • Store Name:

  • Store Number:

  • Store Address and Postcode
  • Store Telephone Number:

  • Store Managers Name:

  • Store Managers contact Number:

  • Store Managers email address

  • Store SAYS Champions Name:

  • Store Champions contact Number

  • Store Trading Hours

  • Mon-Fri

  • Sat

  • Sun

  • Other

  • Does the store have a night shift

  • Night Managers name and contact details

  • Landlord Controlled Site

  • Name & Contact details of the Landlord if applicable

  • Contractors signing in point

  • ANPR Car Park System

  • Location of Visitor Car Reg Input Screen

  • Permit To Work Book location

  • General works access (once signed)

  • Store Drawing ID

  • Photo's of Existing Layout Front End

  • Photo's Proposed Layout Front End

  • Photo's Existing Layout Produce Area

  • Photo's Proposed Layout Produce Area

Detailed Project Scope Of Works:- Removal and Reposition

  • Remove SSC

  • LH Lane type

  • Lane Number

  • Quantity

  • Responsibility

  • RH Lane Type

  • Lane Number

  • Quantity

  • Responsibility

  • Remove Rap Screen

  • Responsibility

  • Remove Assistant / Baby Rap station

  • Responsibility

  • Remove Power/Data Services Poles

  • Lane Number

  • Quantity

  • Responsibility

  • Remove Live Cash Tube Poles

  • Lane Number

  • Quantity

  • Responsibility

  • Remove Signage (SSC / Ten or Less)

  • Quantity

  • Additional Information

  • Responsibility

  • Remove Checkouts / Express etc. With TPF's/Kesslers

  • Checkout Type

  • Lane Number's

  • Quantity

  • Responsibility

  • Ensure all Detaggers are returned with checkouts but leave 1 Detagger for use on SAYS re-scan bench

  • List any missing items from Checkout lanes

  • Remove Checkout IT Equipment

  • Lane Number's

  • Quantity

  • Responsibility

  • Remove Chrome Barriers / Entry Gates

  • Quantity of posts

  • Quantity of Rails

  • Additional Information

  • Responsibility

  • Any Other Removal Works

  • Detail
  • Add media

  • Responsibility

  • Reposition Checkouts / Express etc. with TPF's/Kesslers

  • Checkout Type

  • Checkout Number

  • Quantity

  • Additional Information

  • Responsibility

  • Reposition Checkout IT Equipment

  • Checkout Number

  • Quantity

  • Responsibility

  • Reposition Detagger from existing checkouts (One to be installed on re-scan bench)

  • From Checkout Number

  • To Checkout Number

  • Quantity

  • Responsibility

  • Reposition Flair Pads from existing checkouts (One to be installed on re-scan bench and any remaining need to be handed to Store)

  • From Checkout Number

  • To Checkout Number

  • Quantity

  • Additional Information

  • Responsibility

  • Reposition Hearing Aid Loop

  • From Checkout Number

  • To Checkout Number

  • Quantity

  • Responsibility

  • Reposition Flair Paging Controller

  • From Checkout Number

  • To Checkout Number

  • Responsibility

  • Reposition SSC

  • LH Lane type

  • Lane Number

  • Quantity

  • Responsibility

  • RH Lane Type

  • Lane Number

  • Quantity

  • Responsibility

  • Reposition Rap Screen

  • Screen Version

  • Quantity

  • From Lane Number

  • To Lane Number

  • Responsibility

  • Reposition Assistant / Baby Rap station

  • Baby Rap Version

  • Quantity

  • From Lane Position

  • To Lane Position

  • Responsibility

  • Reposition Live Cash Tube Poles

  • Lane Number

  • Quantity

  • Pole Type

  • Responsibility

  • Reposition Power/Data Services Poles

  • Lane Number

  • Quantity

  • Pole Type

  • Responsibility

  • Reposition Metal Cable Floor Trunking (Between SSC)

  • Lane Number

  • Quantity

  • Trunking Colour

  • Responsibility

  • Reposition Signage (SSC / Basket Checkout)

  • Signage

  • Quantity

  • Photo's

  • Additional Information

  • Responsibility

  • Reposition CCTV Cameras

  • Quantity

  • Additional Information

  • Responsibility

  • Reposition Security Lecturn

  • Quantity

  • Additional Information

  • Responsibility

  • Reposition Produce Mods

  • Quantity

  • Photo's

  • Additional Information

  • Responsibility

  • Reposition Flower or News Stand

  • Quantity

  • Additional Information

  • Responsibility

  • Reposition Fire Extinguishers

  • Quantity

  • Additional Information

  • Responsibility

  • Reposition Disabled Trolleys / Wheel Chairs / Motorised Scooters

  • Quantity

  • Photo's

  • Additional Information

  • Responsibility

  • Reposition Handset Scanner Walls

  • Scanner Wall Variant

  • Photo's

  • Quantity

  • Responsibility

  • Reposition SAYS Network AP

  • Quantity

  • Responsibility

  • Reposition Chrome Barriers / IQM

  • Quantity of IQM posts

  • Quantity of Barrier End posts

  • Quantity of Barrier Mid posts

  • Quantity of Barrier Corner posts

  • Quantity of Rails

  • Responsibility

  • Reposition EAS Checkpoint Gates

  • Quantity

  • Responsibility

  • Any Other Repositioning Works

  • Detail
  • Additional Information

  • Photo's of other works

  • Responsibility

  • PHOTO's

  • Existing SSC

  • Existing Checkouts

  • Existing SAYS

  • Produce Area

Detailed Project Scope Of Works :- Installation of New Equipment

  • Install SAYS payment lanes

  • LH Lane type

  • Lane Number

  • Quantity

  • Responsibility

  • RH Lane Type

  • Lane Number

  • Quantity

  • Responsibility

  • Install Scanner Handset return holders

  • Quantity RH

  • Quantity LH

  • Responsibility

  • Install Metal Power/Data Trunking Between SSC Payment Lanes

  • Colour Specification

  • Quantity (1000mm)

  • Responsibility

  • Install SAYS Scanner Wall

  • Wall Specification

  • Quantity

  • Additional Information

  • Responsibility

  • Install Scanner Å´all Facia Strips

  • Wall strips

  • Responsibility

  • Install 38mm Power/Data pole

  • Pole Position

  • Additional Information

  • Responsibility

  • Install 80x80mm Blanking Plate (Blanking plates in Winchester Oak to cover 38mm hole + screw holes)

  • Quantity

  • Responsibility

  • Install Handsets and Solution (Scanner Wall)

  • Wall Variant

  • Responsibility

  • Install Totem

  • Quantity

  • Additional Information

  • Responsibility

  • Install SAYS Flooring + Dim Strip (Including 10% for cutting & wastage)

  • Additional Information

  • Responsibility

  • Install Signage (Hanging Signage must be installed as not to impede CCTV, AOIF cameras)

  • Quantity of combined SAYS/SSC

  • Quantity (SAYS)

  • Quantity (SSC)

  • Quantity (Basket)

  • Responsibility

  • Install Re-Scan bench

  • 2 Door or 3 Door

  • Responsibility

  • Install SSC/SAYS Corral Woodtech Barrier Rails

  • Responsibility

  • Install Produce Plinths

  • Quantity

  • Responsibility

  • Install Produce Plinth Infills

  • Quantity

  • Responsibility

  • Install 63mm Power/Data pole

  • Quantity (Produce Plinths)

  • Quantity (combined SSC/SAYS)

  • Lane number

  • Quantity (SSC Lanes)

  • Lane Number

  • Quantity (SAYS Lanes)

  • Lane Number

  • Additional Information

  • Responsibility

  • Install Itab manual gates to Super Express checkouts

  • Quantity

  • Responsibility

  • Install Checkpoint EAS tagging gate (SAYS Corral Exit)

  • Quantity

  • Responsibility

  • Install Server in Confidential Room (To be installed the following morning after night 0 as per photo location)

  • Quantity

  • Photo of Location for server unit

  • Responsibility

  • Install New CCTV camera(s)

  • Quantity

  • Additional Information

  • Responsibility

  • Install Chrome Barrier Rail

  • Quantity (Rail)

  • Quantity (End Post)

  • Quantity (Middle Post)

  • Quantity (Corner Post LH)

  • Quantity (Corner Post RH)

  • Responsibility

  • Install Blighline Single mainbank Checkout (only if BTW kit is not available for Itab, GWS, Clairs, ROL, Margo Checkouts)

  • Checkout Type

  • RH or LH

  • Checkout Colour

  • Skirt Colour

  • Responsibility

  • Install BTW kit (Back 2 Wall)

  • Checkout Type

  • RH or LH

  • BTW Colour

  • Skirt Colour

  • Responsibility

  • Install TPF

  • Checkout Type

  • TPF Handing

  • Colour

  • Responsibility

General Builders Works Info - Floor, Ceiling, Access Equipment, Other

  • Any Floor Works Required

  • Floor type

  • Other

  • Floors Works Required

  • If Additional Trench Slabs required (please specify sizes)

  • Additional Information

  • Photo's of Floor

  • Responsible

  • Ceiling Height

  • Any Ceiling Works Required

  • Ceiling Height

  • Ceiling Variant

  • Other

  • Ceiling Tile Type

  • Other

  • Quantity Of Tiles Required

  • Ceiling Track Required

  • Length of Track in metres

  • Responsible

  • Photo's of Ceiling

  • Any Further Building Works Required

  • Responsible

  • Photo's Additional Building Works

  • Access Equipment Required

  • ALS

  • Type of Lifter

  • ISG

  • Type of Lifter

  • Herbert's

  • Type of Lifter

  • Lifter Access Into Store

  • Photo's Of Lifter Access Into Store and Storage area in service yard. (If Using Loading Bay Scissor Lift or Dock Leveller Inc Photo of SWL)

  • Responsible

Cash Tube System Info

  • Cash Tube System Type

  • Overfed / Underfed

  • Cash Tube Cable Tray Working Height

  • Any issues with Cash Tube System

  • Re-number Cash Tube System (if "Yes" Cash Tube Engineer to advise store of till number configuration changes)

  • Photo's of Cash Tube System to include (Controller chip version, Station card, checkout Station etc.)

  • Store to ensure all cash pods are accounted for before ALS commences works on the cash tube system

Delivery Of Hardware

  • Any Delivery Restrictions ?

  • Specify Details

  • Any Parking Restrictions ?

  • Specify Details

  • Any Noise Restrictions ?

  • Specify Details

  • Is the store on stilts

  • Matwell to be covered

  • Responsible

  • Location for delivery vehicle to unload

  • ""NOTE"" Cones and Barriers must be used in car park whilst delivery is being unloaded and loaded

  • Responsible

ISG Technology - Power/Data Details

  • Power & Data route to SSC (Overfed/ Underfed)

  • Power & Data route to Mainbank Checkouts (Overfed/ Underfed)

  • Power & Data route to Produce Plinths (Overfed/ Underfed)

  • Additional Switch required

  • Relocation of power for Checkpoint EAS gate

  • Installation of new power for Checkpoint EAS gate

  • Fuse board Location

  • Location of DP (Distribution Panel)

  • Responsible

Herbert Retail - IT Details

  • Are there any 'Auto One In Front Cameras' that will require switching off ?

  • Checkout Lane Numbers

  • Are there any 'Auto One In Front Cameras' that will require relocating ?

  • Checkout Lane Numbers

  • Are there any new 'Auto One In Front Cameras' required ?

  • Checkout Lane Numbers

  • Are there any new 'Auto One In Front Cameras' that require re-numbering ?

  • Checkout Lane Numbers

  • If applicable Time/Date 'Auto One In Front Cameras' to be switched off or renumbered ?

  • Does the store have Countwise installed that will require removing ?

  • Quantity

  • Does the store have Countwise installed that will require relocating ?

  • Quantity

  • Any additional Countwise cameras required ?

  • Quantity in meters

  • Is there any new cable tray work required ?

  • Quantity in meters

  • Is there any existing cable tray work to be reconfigured or relocated ?

  • Quantity in meters

  • Are there any bioptic scanner scales to be calibrated ?

  • Lane numbers

  • Are there any bioptic scanner scales to be verified ?

  • Lane numbers

  • If applicable Time/Date 'Auto One In Front Cameras' to be switched off or renumbered ?

  • Responsible

Wincor - New IT Equipment

  • Are there any new tills being installed that will require new/refurb till and scales

  • Lane numbers

  • If Renumbering of existing tills is required then it must be arranged with Wincor...... NOTE:- Renumbering can only commence on a Sunday night.

  • Responsible

EXTRAS (State clearly here anything that is outside the SAYS scope to inc any special requests from the store manager)

  • Are there any EXTRAS (State clearly here anything that is outside the SAYS scope to inc any special requests from the store manager)

  • Detail of Extra works requested

  • Photo's of Extra works requested

  • Responsible

  • Surveyors signature on completion

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.