SCOPE OF WORKS

  • Concreter to confirm dates and meet the dates suggested

  • read plans in conjunction with soil report and engineering looking for RFM specified

  • liase with Building inspector to arrange pre slab and steel inspection

  • steel and concrete to be installed in conjunction with the AS2870 slab standards

  • call up termite if relevant per job

  • arrange booking for concrete as per desired timelines

  • concrete to be installed as per as 3600 well vibrated and steel trowell finish

  • arrange plumber slab check two day prior to boxing with completed boxing in place

  • Plumb meter box to external wall both ways

  • install plumber boxes to shower and bath tub when required

  • all external concrete slabs to have Fall and no ponding water , with non slip finish

  • smart pans and wastes to be installed 5mm below slab level

  • Arrange electrician for all electrical conduits if required

  • install metal keyway to construction join using stickyback able flex to one side for expansion when required

  • plumber to be called up for any pipe breakages to avoid hefty repairs and costs after pour

  • garage weather strip to be 25-30mm step down 120mm behind and beside brick . Fall out tray to fall out and not hold water

  • clean site perimeter to nominated EGL and bring all dirt forward to be accessible for removal

  • arrange for supervisor to remove spoil after slab pour, or prior to pour .

  • additional reo to be removed or cut and placed in bin

  • install wet earth stake to power pole in slab

GJ GARDNER OH&S

  • sign in Hazard co app

  • keep SWMS on site at all times

  • current Public liability and White card up to date and sent to GJ Gardner office

  • HSCP in Meter box of house unless otherwise specified by the site manager

  • site to be left in a safe manner . All rubbish picked up and placed in bin or in a bag beside the bin if the bin is full

  • trades to be courteous and respectful to adjoining properties and neighbours

  • Trades not to be instructed by customers and Customers are not to be let in to site

G J GARDNER PAYMENT

  • Purchase orders to be handed in with all invoices emailed to geelong.accounts@gjgardner.com.au

  • All extras to have an attached Manual order number from the site managers and must be invoiced separately

  • Invoices as per purchase order unless otherwise discussed

TRADES ACKNOWLEDGEMENT

  • Trade acknowledgement and acceptance

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.