Slab Manager slab check pre pour

  • arrange for Concreter to confirm dates and meet the dates suggested

  • read plans in conjunction with soil report and engineering looking for RFM specified

  • liase with Building inspector to arrange pre slab and steel inspection

  • check steel to be installed in conjunction with the AS2870 slab standards

  • confirm call up termite if relevant per job

  • confirm booking for concrete as per desired timelines

  • arrange plumber slab check two day prior to boxing with completed boxing in place

  • Plumb meter box to external wall both ways

  • install plumber boxes to shower and bath tub when required

  • smart pans and wastes to be installed 5mm below slab level

  • Arrange electrician for all electrical conduits if required

  • install metal keyway to construction join using stickyback able flex to one side for expansion when required

  • plumber to be called up for any pipe breakages to avoid hefty repairs and costs after pour

  • plumber to camera sewer prior to pour

  • ensure that all spoil is removed or booked to be removed . Check contract is dirt is to be left on site

  • additional reo to be removed or cut and placed in bin by concreters

  • install wet earth stake to power pole in slab

  • confirm that all formwork is located as per site plan .

  • confirm that all measurements are correct

GJ GARDNER OH&S

  • sign in Hazard co app

  • keep SWMS on site at all times

  • current Public liability and White card up to date and sent to GJ Gardner office

  • HSCP in Meter box of house unless otherwise specified by the site manager

  • site to be left in a safe manner . All rubbish picked up and placed in bin or in a bag beside the bin if the bin is full

  • trades to be courteous and respectful to adjoining properties and neighbours

  • Trades not to be instructed by customers and Customers are not to be let in to site

G J GARDNER PAYMENT

  • Purchase orders to be handed in with all invoices emailed to geelong.accounts@gjgardner.com.au

  • All extras to have an attached Manual order number from the site managers and must be invoiced separately

  • Invoices as per purchase order unless otherwise discussed

TRADES ACKNOWLEDGEMENT

  • Trade acknowledgement and acceptance

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.