Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Select date
-
Add location
-
WEATHER
-
SITE CONDITIONS
-
TRAFFIC MANAGEMENT
-
FENCING & WHS SIGNAGE
Safety - Earthworks, Excavation
-
Does the contractor have utilities / services plans on site.
-
Does plant and equipment have suitable warning lights and reversing beepers
-
Are personnel in the vicinity of operating plant wearing high vis clothing and helmets where required.
Environmental - Earthworks, Excavation.
-
Is there provision to minimize dust / mud from leaving the site.
-
Do stockpiles have adequate silt runoff protection.
-
Are environmental No Go areas fenced where required.
-
Are silt traps in place to prevent silt build up in previously installed drainage system.
Sewer Works
-
Sewer Contractor Onsite
-
Does the contractor have issued for construction drawings and the latest revision
-
Are materials stored correctly on site
Works - Trenching, Pipelaying, Backfill, Surface Fittings
-
Pipeline Percentage Complete
- PC Achieved
- 100
- 90
- 80
- 70
- 60
- 50
- 40
- 30
- 20
- 10
- Not Started
-
Is there an accredited pipe layer on site.
-
Are trench widths adequate for pipe size/ type
-
Comments
-
Is the bedding material & thickness within tolerance and being compacted correctly
-
Are pipes being installed in accordance with design specification and manufacturers recomendations.
-
Are clearances to other services being maintained as per specification.
-
Does trench backfill material comply with standard drawings and specifications
-
Are lids / covers as per design and set correctly.
-
Comments
Safety - Trenching, Pipelaying, Backfill, Surface Fittings
-
Does the contractor have utilities / services plans on site.
-
Does plant and equipment have suitable warning lights and reversing beepers
-
Is ground support suitable for the ground conditions and depth of excavation
-
Are workers provided with a ladder or other means of access and egress where required.
-
Are hats and vests being worn by workers where required
-
Are trenches barricaded and made safe when left open.
-
Is lifting equipment suitable for the works being carried out.
Comments/ Progress/ Instructions
-
Sketch of Work Area (Optional)
-
Comments
-
Photos
-
Prepared by