Title Page
-
Site conducted
-
Client
- Neath Port Talbot County Borough Council
-
Principal Contractor
-
Site Foreman/Manager
-
Inspection Conducted on
-
Inspection Prepared by
- Adam Cavanagh - SHEQ Manager TVC
-
Location
-
Weather conditions
- Sunny
- Cloudy - Overcast
- Rain - Showers
- Rain - Heavy
- Hail
- Snow
-
Current work activities
-
Actionable items from previous report closed out?
-
Are there Risk Assessments & Method Statements approved
-
Are they Suitable and sufficient for the works being carried out and signed by all operatives involved in it’s entirety with regular monitoring of changes to processes or materials.
-
All works MUST stop until suitable and sufficient Risk assessments are in place, signed & approved
-
All WORKS regarding those RAMS must stop until suitable and sufficient RAMS have been supplied and approved
-
Have all Operatives and Visitors been given a Safety Induction
-
Is CoSHH suitably stored and controlled at site level
- CoSHH boxes suitable for the chemicals stored
- CoSHH boxes unsuitable for storage materials
- CoSHH elements onsite have nappies placed underneath, and dry.
- CoSHH elements onsite have nappies placed underneath, but are wet which will hinder its soaking ability leading to spillage
-
Dust and Noise suitably controlled
-
Is Hand Arm Vibration being controlled and adequately managed with active HAVS monitoring.
-
PUWER register Daily/weekly check sheets for Plant & Equipment?
-
Are there relevant operatives training records & competency cards?
-
Have tool box talks/safe briefings been delivered?
-
Are Fire/Emergency notices/equipment displayed?
-
Are welfare facilities provided and are adequate & clean?
-
Are first aid provisions and equipment provided?
-
Is there a Defibrillator onsite or near site that can be used in an emergency.
-
Are Certificates in place for temporary electricity in cabins.
-
Are PAT registers for the tools and equipment in place.
-
Is the suitable and sufficient Task lighting.
-
Is there a Traffic Management/Logistics plan displayed?
-
Does the traffic management plan mirror site traffic management.
-
Is the traffic management being adhered to onsite.
-
Are Access & Egress Routes in good order?
-
Are Excavations being managed correctly?
-
Is housekeeping/material storage compliant?
-
Are there suitable Waste Management Procedures in place? Recording of waste Transfer notes.
-
Is the use of Access Equipment Compliant ? (Scaffold, Towers, MEWPS etc)
-
Is working at Height suitably controlled
-
Are all Leading Edges & Potential Falls from Height suitably protected?
-
Has all edge protection got the TVC logo on show in good condition and legible.
-
Remove damaged / untidy or faded edge protection and replace with compliant panels
- Panel/s changed for new panels at time of inspection
- Panel/s could not be changed at time of inspection - no suitable panels onsite, waiting for more to be delivered.
-
Are there Lift plans present and correct along with corresponding certificates for lifting equipment & accessories, plant and equipment thorough examinations in place?
- Lift plans supplied and approved through TVC
- Lift plans supplied and approved through Knights Brown
- Lift plans supplied and approved through a third party
- Lifting equipment and accessories with correct tags and in date
- Lifting equipment and accessories without the correct coloured tags and out of date
-
Is Safety equipment & PPE being used correctly? Correct fitting PPE etc
-
Is RPE being worn on site ?
-
Does the operative have face fit training for the mask he is wearing
-
If NO Face Fit training for the mask being worn then they are required to stop works and someone who has the correct training to continue.
-
Are they clean shaven - the requirement is to be clean shaven at ALL times when wearing RPE.
-
Does this site have security/prevention of unauthorised access?
-
Is there adequate site signage (directional,warning, safety etc) on this site?
-
Were the work areas found to be in a safe, compliant condition?
-
Are gas bottles & flammable stored and used safely?
Actionable items - Risk & Hazards seen at site level.
-
Areas/Items of Risk.
-
Recommendation
-
Time Frame to close out
- Low Risk - 1 week
- Medium Risk - 3 days
- High risk - Immediately or stop works in this area until it is safe to continue
Sign off
I confirm that I have read and discussed the issues raised with the auditor.
-
Project/Site Manager
undefined
-
Person conducting this Audit.