Title Page

  • Ensure the visit is started in OFSC

Install Details

  • Install start date:

  • Finish date:

  • Total duration:

  • Summary completed by:

Customer Details

  • For data protections purposes, please only use initials and first part of the postcode.

  • Customer initials:

  • First part of postcode only:

  • Property type:

  • How many floors to the property?

System Details

  • DNO status:

  • Inverter make & model:

  • Number of panels:

  • Panel wattage:

  • Total panel output:

  • Number of arrays:

  • Batteries:

  • Total battery kWh:

  • Bird protection:

Installation Team

  • For data protection, please only use SIS numbers

  • Lead Electrician:

  • Other Electricians:

  • Lead Solar PV Installer:

  • Other Solar PV Installers:

Parking & Access restrictions

Parking restrictions

  • Is there available parking for the installation team?

  • If yes, what type of parking is available?

  • If no, what parking restrictions are there?

Access restrictions

  • Are there any access restrictions at the property?

  • What access restrictions are there?

  • Can all the access restrictions be removed or controlled? If not please escalate

  • After escalation, can all the access restrictions be removed or controlled?

Risk Assessment

  • Does the customer have any COVID like symptoms?

  • Does the customer require the wearing of face coverings?

  • What external hazards have you identified?

  • What actions have been carried out based on the external hazards identified?

  • What internal hazards have you identified?

  • What actions have been carried out based on the internal hazards identified?

  • After any escalations, can you now proceed safely with the task?

MMHG Delivery Checklist

  • After checking the delivery, was the order complete?

  • If no, what items were missing? Please provide name of item and quantity

  • How were the missing items replaced?

  • Did the missing items have an impact on the installation duration?

Working at height

  • What access platform is to be used on this installation?

  • What ladder will be used to access the platform?

  • Is the loft going to be accessed on this installation?

  • What ladder will be used to access the loft?

  • Does the installation require the use of a ladder to secure cable?

  • What ladder was used to secure cable?

Safe systems of work

  • Can the installation be completed following our safe systems of work? If not please escalate

  • After escalating, can the installation be completed following our safe systems of work? Add note with details of who the escalation was made to, the details of the escalation and the outcome.

Personal Protective Equipment

  • Can you confirm that the correct PPE can be worn to complete this visit? If not please escalate

  • After escalating, can the installation be completed with the correct PPE? Add note with details of who the escalation was made to, the details of the escalation and the outcome

External roof inspection

  • If you select 'Yes' to highlight any issues in this section, it is important that you take a photograph and add a note to the question.

External roof inspection

  • Please upload a photograph of each roof that is going to be accessed during the installation

  • Are there any visual defects to the roof?

  • Is there any damage to the gutter, fascia or soffits?

  • Are there any missing tiles?

  • Are there any damaged tiles?

  • Are there any missing ridge tiles?

  • Are there any damaged ridge tiles?

  • Are there any dips in the roof section?

  • Are there any dips in the ridge section?

  • Are there any chimneys on or near to the install section of the roof?

  • If there is a chimney, is it in good condition?

  • Are there any roof vents or roof windows on or near to the install section of the roof?

  • If there are any roof vents or roof windows, are they in good condition?

  • Are there any roof obstacles that are not shown in the installer pack sent by MMHG? If yes add note with details

  • Using your current training and processes, will any of the above issues prevent a safe install? If no, please escalate

  • After escalation, will any of the above issues prevent a safe install?

Internal roof inspection

  • Is the underside of the roof accessible?

  • Any signs of damage to the underside of the roof?

  • Is there a roof felt or membrane installed?

  • Is the roof felt or membrane in good condition?

  • Is there any light leakage through the roof?

  • Are there any signs of rot or damp?

  • Are there any signs of pest infestation?

  • Are there any signs of the roof sagging?

  • What is the distance between rafters? (in millimetres)

  • What is the size of the rafters? (in millimetres, width and depth)

  • Is there fixed lighting in the loft?

  • Is the loft boarded?

  • Will any of the above issues prevent a safe install? If so please escalate

  • After escalation, will any of the above issues prevent a safe install?

Solar Panel Installation

  • Important: Take a photo of the serial number of every solar panel that is to be installed.

  • Can the solar panels be installed exactly as detailed in the installer pack?

  • If no, please provide details of why the solar panels cannot be installed as detailed in the installer pack:

  • Roof tile type

  • Will the tiles require notching to allow flush fitting over the roof anchors?

  • Please upload photos of roof before installation, showing any defects or damage on close ups. If multiple arrays are to be installed, repeat for each roof aspect

  • If the solar panels are to be installed within 400mm of a roof edge, have additional roof anchors been used?

  • If any of the panels require optimisers, have the barcodes and positions of the panels and optimisers been captured for MMHG? Take a photo of the panels where optimisers have been installed, marking them with Skitch/Sketch up

  • Please upload photos of panels installed on roof. If multiple arrays have been installed repeat for each roof aspect

  • Have the solar panels been cleaned down after installation?

  • Are all the solar panels installed level and aligned?

  • If there have been any broken tiles, have they been replaced?

  • Have all roof tiles been pulled back down into the correct position and the roof left watertight?

  • Has all the DC cabling been secured to the rails and not left on the roof?

  • Have all 20mm holes for access equipment been plugged?

  • If we have provided any additional consumables please list them here, and the quantities used:

  • Please provide details of any issue that you encountered during this installation

  • Please provide details of any learnings that you have gained from this installation

  • Did you have to escalate any issues? If so please provide details of the escalation, who you escalated to and what the outcome of the escalation was.

  • Has all SIS generated waste been removed from the outdoor areas of the site ready for return to UL?

Electrical installation

  • Please ensure safe isolation procedure is followed before working on the consumer unit

  • Incoming electricity supply type:

  • Make of main consumer unit?

  • Is there space on the main consumer unit to install solar?

  • Please upload photos of the main consumer unit:

  • Is there an DNO isolation switch?

  • Please upload photos of the incoming electricity supply including electricity meter, DNO fuse and isolation switch (if present)

  • Is an additional garage board being used?

  • Are you able to carry out a Zdb test?

  • Is there earth bonding to the mains water and mains gas? Please upload photos

  • Are you able to carry out an earth bonding continuity test?

  • Take a photo of the Inverter serial number:

  • Inverter location:

  • Is the inverter being installed in the same location as the main consumer unit?

  • Take a photo of the EMliteEML generation meter serial number:

  • What AC cable will be used to connect the inverter?

  • How will the AC cabling be installed?

  • Please upload photos of the inverter location, prior to commencing install

  • Please list all electrical consumables used on this installation and the quantity of each item:

  • Please upload photos of the finished installation. Photos must include: Inverter, DC isolators, AC isolators, generation meter, main consumer unit, batteries (if installed), garage board (if installed), DC cabling route, AC cabling route

  • Have all serial numbers for panels, optimisers and inverter been captured?

  • Have all electrical safety labels been affixed in the correct places?

  • Please provide details of any issue that you encountered during this installation:

  • Please provide details of any learnings that you have gained from this installation

  • Did you have to escalate any issues? If so please provide details of the escalation, who you escalated to and what the outcome of the escalation was.:

  • Has all SIS generated waste been removed from the indoor areas of the site ready for return to UL?

Testing & Documentation

DC Testing

  • Has DC polarity been confirmed with the clamp meter?

  • Has an Irradiance test been completed?

  • Has a string open circuit voltage (VOC) test been completed?

  • Has a string circuit current (ISC) test been completed?

  • All DC Isolators tested?

  • Has an Insulation Resistance Test of the PV strings been completed?

AC Testing

  • All AC Isolators tested?

  • Has a continuity test of the PV circuit been completed? (R1 + R2)

  • Has an insulation resistance test of the PV circuit been completed?

  • Has the continuity and IR test confirmed polarity?

  • Have you tested the Zs?

Documentation

  • Has a minor works certificate been completed on NAPIT Fast Test?

  • All test results from DC and AC added to the minor works certificate?

  • Have all the Solar PV system details been added to the MMHG Portal?

Damage

  • Has any damage occurred during the installation visit? If yes please add note and upload photos

  • Can all damage be repaired by the installation crew?

  • Has any damage that cannot be repaired by the installation crew been escalated using the correct process?

Customer handover checklist

Solar Panels

  • - Highlight the neat layout of the panels, either as original plan or improved plan

  • - Highlight that all roof tiles have been replaced, any broken tiles have been fixed, all tiles have been notched to ensure a weathertight seal, and that all tiles are sat correctly with no gaps showing on the underside.

  • - Highlight that all the DC cabling on the roof has been secured off the roof and under the panels

  • - If any optimisers have been installed, highlight these panels to the customer for their awareness

  • - Inform the customer that all the panels have been secured to the regulatory standards

  • - Let the customer know that you have cleaned down all panels after installation to ensure peak performance

  • - Show the customer that all 20mm holes used for access equipment have been plugged and sealed

External cabling

  • - Mention to the customer that all external wiring has been secured to the latest wiring regulations

  • - Highlight neat and tidy cable runs

  • - Show the customer that all cable entry points have been sealed with with a drip loop to prevent water ingress

  • - If any conduit has been installed externally, ensure the customer is aware of what cables are in the conduit and aware of any risks

Internal cabling and electrical installation

  • - Show the customer all the internal cable runs either in conduit or surface mounted, mentioning that all internal wiring has been secured to the latest wiring regulations

  • - Show the customer the electrical components and explain their purpose (Inverter, Isolators, Generation Meter). Also explain how they can isolate the components in event of an emergency.

  • - Highlight your installation skills

  • - If batteries are installed explain their purpose and the options available to charge them

  • - Talk the customer through the inverter display

  • - Ensure the customer has the right app for controlling their inverter settings

Final handover

  • Explain customer escalation paths if they need any tech support in the future

  • - Ask if they are happy with the work you have carried out for them, and if they need you to do anything else for them

  • - Let the customer know they will receive a customer feedback survey based on the installation visit by yourself and that you'll appreciate them taking the time to complete this for you

  • - Let the customer know you will just have one last walk around to ensure the site is left in a clean and tidy state. Carry out a full site inspection to make sure their is no SIS generated waste

Any other feedback

  • If there is any other feedback not captured already in this document, please add it here:

  • Upload this document and EIC document to MS Teams group. Ensure the visit is closed in OFSC

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.