Title Page
-
Substation
-
Date
-
Leaks (air, gas, and/or oil - include the equipment leaking, where, and severity)
-
Operation of breaker air compressor(s) checked (if applicable)
Nitrogen pressure
-
unit
-
Unit
-
Tank pressure
-
XFMR pressure
-
General coverall primary equipment condition ( transformers, breakers, switches, PTs, CTs, insulators, etc.)
-
General overall yard condition (cable through, security problems, etc.)
-
General overall control house condition (doors, windows, lighting, etc.)
-
Condition of capacitor banks (leaks, bulged cans, blown fuses, etc.)
-
If the capacitor cans are PCB and leaking, notify ESO immediately for corrective action by substation construction & maintenance
-
Battery water level between the high and low lines (if not, identify the cell # and water level)
-
Fire extinguisher condition
-
Fire extinguisher date
-
Fire extinguisher initial card
-
DC grounds checked
-
All trash removed
-
Comments
-
Inspected by
-
Date