Information

  • Document No.

  • Audit Title

  • Project

  • Cubicle

  • Product

  • SN Cubicle

  • Client / Site Plan

  • Conducted on

  • Prepared by

  • Personnel

Package Verification

  • Packing with full wooden

  • Reference : Standard

  • Delivery to information

  • Reference : Project Information

  • Gross weight information<br>(Kgs)

  • Reference : Cubicle information

  • Nett weight information<br>(Kgs)

  • Reference : Cubicle information

  • Consignee name<br>information

  • Reference : Project Information

  • Case number information

  • Reference : Logistic information

  • Umbrella mark<br>information

  • Glass mark information

  • Dart mark information

  • Sling mark information

  • Sea worthy packing

  • Used aluminium foil

  • Woods thickness

  • Silica gel

  • Others

  • Others Inspection
  • Others

  • Reference :

Visual Inspection

  • a) Visual inspection for aesthetic quality, painting, labels, wiring neatness etc.

  • b) Verification of cubicle against customer requirements, drawings, BOM.

  • LV Box Spec Component<br>check

  • Reference : Bill of material /
    Component list

  • LV Component layout

  • Reference : Layout drawing

  • LV Name plate & Name<br>tag

  • Reference : Schematic drawing

  • LV Component label

  • Reference : Schematic drawing

  • Wires marker

  • Reference : Schematic drawing

  • Wiring crimping

  • Reference : Standard Crimp Guide

  • Wiring Tightness

  • Reference : Standard catalogue

  • Painting check

  • Reference : Surfacing condition

  • CT Specification

  • Reference : SLD & Comp List

  • VT Specification

  • Reference : SLD & Comp List

  • Verification SLD<br>Specification

  • Reference : SLD drawing

  • Contactor / Circuit<br>Breaker

  • Reference : SLD & Comp List

Simulate Site Condition

  • Couple cubicle & check for non-conformance, if any
    Note : This need two cubicle for simulation, bolt for cubicle jointing and main
    busbar preparation

  • Cubicle joint installation

  • Main Busbar Installation

  • Earthing busbar Installation

  • Fastening Link Installation

  • LV intercubicle access

  • Others Inspection

Check Mechanical & Electrical Functionality (Including Interlocks)

  • a) Check electrical functionality as per the schematic drawing

  • b) Check mechanical functionality like indications, earth switch operation, shutter
    operation, rack-in rack-out, and door operation

  • Frame right & Left /<br>Dimension

  • Bolt fixing untighten &<br>missing

  • Configuration bottom &<br>cable connection

  • Cassette Checking<br>Operation (shutter<br>operation)

  • Codding CB / Interchangebility

  • Mechanism door ( Middle<br>door & Lower Door )

  • Interlocking System / Key<br>Locks individual

  • Checking Rack-in and<br>Rack-out CB for 5 times<br>operation

  • Checking Shutter Fully<br>Open and Fully closed<br>condition

  • CB Manual spring charge<br>operation

  • Close-Open CB operation

  • ES Closing operation

  • ES Opening operation

  • CB at test position, Check<br>interlocking LV Plug with<br>CB handle lever

  • ES Closed, CB Cannot<br>rack-in to sevice position

  • ES Lever cannot open<br>when CB has left of CB test<br>position

  • Intermediate/not fully<br>service position CB cannot<br>closed

  • Midlle door cannot open<br>when CB on service<br>position

  • CB at service position and<br>closed position, handle<br>cannot inserted

Electrical Functionality, Complete Routine Tests (Refer PTP PIX, Control Plan MCset)

  • a) Check electrical functionality as per the schematic drawing

  • b) Check interlocks functionality

  • c) Carryout complete routine tests

  • d) Resistance of the main circuit

  • Function of Heater

  • Function of Control<br>Circuit

  • Function of Remote<br>Control

  • Function of Signaling

  • Dielectric test on main<br>circuit

  • Insulation Resistance

  • Drop voltage / Ducter test

  • Visually connected or<br>check with continuity test<br>to earth

  • Auxiliary circuit<br>dielectric test (1KV / 1s)

  • Functional relay

  • Functional Power Meter

  • Test metering

  • Others Inspection

6. Manufacturing & Process Quality Control (Refer Assembly Instructions)

  • Verify manufacturing & quality control traceability at each stage of manufacturing

  • Item / Process Check
  • Item / Process Check

  • Verify quality control traceability for critical parts at incoming inspection (Refer<br>Critical Parts Management Process)

  • Item / Process Check
  • Item / Process Check

Summary

  • Summary Result

  • Auditor

  • Audity

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.