Information
-
Document No.
-
Audit Title
-
Project
-
Cubicle
-
Product
-
SN Cubicle
-
Client / Site Plan
-
Conducted on
-
Prepared by
-
Personnel
Package Verification
-
Packing with full wooden
-
Reference : Standard
-
Delivery to information
-
Reference : Project Information
-
Gross weight information<br>(Kgs)
-
Reference : Cubicle information
-
Nett weight information<br>(Kgs)
-
Reference : Cubicle information
-
Consignee name<br>information
-
Reference : Project Information
-
Case number information
-
Reference : Logistic information
-
Umbrella mark<br>information
-
Glass mark information
-
Dart mark information
-
Sling mark information
-
Sea worthy packing
-
Used aluminium foil
-
Woods thickness
-
Silica gel
-
Others
Others Inspection
-
Others
-
Reference :
Visual Inspection
-
a) Visual inspection for aesthetic quality, painting, labels, wiring neatness etc.
-
b) Verification of cubicle against customer requirements, drawings, BOM.
-
LV Box Spec Component<br>check
-
Reference : Bill of material /
Component list -
LV Component layout
-
Reference : Layout drawing
-
LV Name plate & Name<br>tag
-
Reference : Schematic drawing
-
LV Component label
-
Reference : Schematic drawing
-
Wires marker
-
Reference : Schematic drawing
-
Wiring crimping
-
Reference : Standard Crimp Guide
-
Wiring Tightness
-
Reference : Standard catalogue
-
Painting check
-
Reference : Surfacing condition
-
CT Specification
-
Reference : SLD & Comp List
-
VT Specification
-
Reference : SLD & Comp List
-
Verification SLD<br>Specification
-
Reference : SLD drawing
-
Contactor / Circuit<br>Breaker
-
Reference : SLD & Comp List
Simulate Site Condition
-
Couple cubicle & check for non-conformance, if any
Note : This need two cubicle for simulation, bolt for cubicle jointing and main
busbar preparation -
Cubicle joint installation
-
Main Busbar Installation
-
Earthing busbar Installation
-
Fastening Link Installation
-
LV intercubicle access
-
Others Inspection
Check Mechanical & Electrical Functionality (Including Interlocks)
-
a) Check electrical functionality as per the schematic drawing
-
b) Check mechanical functionality like indications, earth switch operation, shutter
operation, rack-in rack-out, and door operation -
Frame right & Left /<br>Dimension
-
Bolt fixing untighten &<br>missing
-
Configuration bottom &<br>cable connection
-
Cassette Checking<br>Operation (shutter<br>operation)
-
Codding CB / Interchangebility
-
Mechanism door ( Middle<br>door & Lower Door )
-
Interlocking System / Key<br>Locks individual
-
Checking Rack-in and<br>Rack-out CB for 5 times<br>operation
-
Checking Shutter Fully<br>Open and Fully closed<br>condition
-
CB Manual spring charge<br>operation
-
Close-Open CB operation
-
ES Closing operation
-
ES Opening operation
-
CB at test position, Check<br>interlocking LV Plug with<br>CB handle lever
-
ES Closed, CB Cannot<br>rack-in to sevice position
-
ES Lever cannot open<br>when CB has left of CB test<br>position
-
Intermediate/not fully<br>service position CB cannot<br>closed
-
Midlle door cannot open<br>when CB on service<br>position
-
CB at service position and<br>closed position, handle<br>cannot inserted
Electrical Functionality, Complete Routine Tests (Refer PTP PIX, Control Plan MCset)
-
a) Check electrical functionality as per the schematic drawing
-
b) Check interlocks functionality
-
c) Carryout complete routine tests
-
d) Resistance of the main circuit
-
Function of Heater
-
Function of Control<br>Circuit
-
Function of Remote<br>Control
-
Function of Signaling
-
Dielectric test on main<br>circuit
-
Insulation Resistance
-
Drop voltage / Ducter test
-
Visually connected or<br>check with continuity test<br>to earth
-
Auxiliary circuit<br>dielectric test (1KV / 1s)
-
Functional relay
-
Functional Power Meter
-
Test metering
Others Inspection
-
6. Manufacturing & Process Quality Control (Refer Assembly Instructions)
-
Verify manufacturing & quality control traceability at each stage of manufacturing
Item / Process Check
-
Item / Process Check
-
Verify quality control traceability for critical parts at incoming inspection (Refer<br>Critical Parts Management Process)
Item / Process Check
-
Item / Process Check
Summary
-
Summary Result
-
Auditor
-
Audity