Team Board: Communication and Problem Resolution Process
-
Current Management LPA results (completed within the last month) are recorded in the 'Management LPA Review' section.
-
The Management Board Review was completed in the previous week.
-
Numeric and Red/Green shift results for the last 24hrs have been recorded.
-
Where target has not been met, an explanation exists including occurrence date, containment/corrective actions and owner.
-
All SQTCM (Safety, Quality, Timing, Cost, Motivation) and audit-related actions listed on the front of the board are also captured on the appropriate Actions Log inside the board.
-
5S & SWI Audit results have been updated to Schedule/Trend Graphs.
Team Member Process Checks
-
Have all Ops completed pre-shift safety inspection (where applicable)?
-
Are all Ops current on their 5S tasks (where applicable)?
-
Are previous day's TPM signoffs current (where applicable)?
Area Specific Contents (As determined by Area TL with Quality Support)
-
Are rework operators inspecting parts for TPO residue and using a 1500 foam pad to remove?
-
Does the paint label match the scribe on part (LH vs RH)?
-
Are the post protectors being used when unloading moulded WIP racks?
-
Are racks at load deck one level high at most? (Not stacked)
-
Please enter Auditor's Signature