Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
Day 1 work
-
Is Work in progress
Electrical / Mechanical Installation
-
Hang SC control Panel<br>
-
Hang VAV transformers<br>
-
Wire RTU1, WCI, OA Building Static, fire alarm<br>
-
Wire RTU2, WCI, RA RH, fire alarm<br>
-
Install and / wire WCI 1 and 2<br>
-
Pull VAV 24vac power<br>
BAS Progress
-
Meet with EC install contractor and review install proces and priorities
-
Review iAuditor with PM
-
Address iAuditor findings with MC as necessary after talking with PM
-
Mount Controllers in panel.
-
Email progress to PM
Day 2 work
-
Is Work in progress
Electrical / Mechanical Installation
-
Pipe and pull wire Boilers/Pumps
-
Wire VAV's, Power, DAT, HWV, check WCI address, check all connections
-
complete blr room terminations
BAS Process
-
Get SC license installed in SC. Setup SC.
-
Program/Set Up RTU's
-
Program HW System UC-600
-
Work with Local office Start Up Tech on RTU's
-
Start working on graphics.
-
Start working on graphics.
-
Supervise EC install
-
Meet with MC regarding issues to complete for start up
Day 3 work
-
Is Work In progress
Electrical / Mechanical Installation
-
Install and wire router
-
Pull wire for Freezer Alarm
-
Pull wire for Freezer Temp
-
Wire UH Fan/control Valve
-
Install and Wire Garage Door contact
-
Wire EF
-
complete freezer temp termination
-
complete freezer alarm termination
-
install thermostats
-
Label Grid
BAS Progress
-
Program/Label Stats
-
Install VAV controllers into SC.
-
Place points out of service on VAV boxes and setup RTU controllers.
-
Work with local office start up tech on RTU's
-
Program ventilation set-points into all VAV boxes.
-
Work on graphics
-
Supervise EC Install
-
Email progress to PM
Day 4 Work
-
Is Work in progress
Electrical / Mechanical Installation
-
Everything done on day 1, 2, 3 or 4
-
assist with system check out
BAS Progress
-
Perform system checkout
-
Perform combustion analysis
-
Work on Alarming
-
Supervise EC on Boilers
Day 5 Work
-
Is Work in progress
Electrical / Mechanical Installation
-
Everything done on day 1, 2, 3 or 4
-
assist with system check out
BAS Progress
-
Completed Overview of system operation.
-
Email progress to PM
-
Has the As-Built's been Emailed to the PM
-
Add signature