Title Page

  • Date that the delay was identified:

  • Name of person completing this form:

  • FFP area(s) this Delay Noticement affects:

  • What is the root cause of the delay, pursuant to clause 12.9 (a).(i)?

  • Are there any other of the delay, pursuant to clause 12.9 (a).(i)?

  • What is the expected effect of the delay, pursuant to clause 12.9.(a).(iii): IE Subcontract build partners are being disrupted during the build phase OR VPL is being delayed due to an inability to complete the cabinet

  • What is the expected duration of the delay, pursuant to clause 12.9.(a).(ii) (in days): Please note if the delay may have a compounding effect on resourcing with other areas.

  • Is there likely to be a Financial implication?

  • If yes, provide an estimated value of the cost and/or quantities

  • Provide the steps being taken to avoid the delay, pursuant to 12.9.(a).(v)

  • Where applicable, provide photo evidence of the cause of delay. For example damaged ducts

  • Where applicable, provide a photo of the updated asbuilt recorded by the contractor. For example, for a new duct added.

  • Where applicable, provide photos off additional supporting evidence such as timesheets or the STMS 2 hourly checksheets.

  • Provide any other supporting comments for this notice.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.