Information

  • Audit title

  • Serial number

  • Serial number

  • Client / Site

  • Start time

  • Prepared by

  • Location
  • Mandatory site pictures

Commissioning Report

At the time of the initial diagnostic/ Commissioning mobilization, the Technician will note any deficiencies in the existing system regarding compliance with UL325 standards and advise the customer of same. Systems that do not comply with current UL325 standards may or may not be commissioned at this time at our discretion. Technician will also determine at that time if the requested commissioning shall need to be rescheduled.

PERFORMANCE VERIFICATION TESTS

  • Below is a list of Required Items that will be needed to complete the PVT.
    1) Safety vest
    3) Verify Contractor will have at least TWO (2) radios/walkie-talkies.
    4) Verify Contractor will have flag-persons if ACP (Access Control Point) is not being closed.
    5) Pad of paper and pen or pencil
    6) If still active construction site, verify a hard hat is required.
    7) If still active construction site, verify steel toed boots will be required.
    8) Copy of any pertinent drawings and/or specifications
    9) Vehicle or four pieces of sheet metal (minimum size equivalent to a laptop computer) for AVB
    (Active Vehicle Barrier) Safety Loop Detector Testing.
    10) Measuring Tape

  • ATTENDANCE ROSTER (Training portion)

  • Add signature

  • Add signature

  • Add signature

  • Add signature

  • Add signature

  • Add signature

  • Add signature

  • Add signature

  • Add signature

  • Add signature

  • Testing conditions (Weather, Temperature, etc)

  • Serial number

  • Number of Gates across roadway/Inbound

  • Number of Gates across roadway/Outbound

  • Is the Power Unit Cabinet protected from vehicle impact?

  • Location of Controller

  • Is there a generator on site?

Electrical

  • Audible warning device (horn) when gate is in motion, horn should be on

  • Conduits- All conduits going into the enclosures should be installed as per electrical codes into the bottom of the enclosures only

  • Add media

  • Encoder- The encoder should be securely fastened to the motor shroud fan. There should be no noise/ gate movement resistance when gate is manually/ automatically operated

  • Add media

  • Operators- Ensure that all wiring is properly terminated. Any unused wires should be properly isolated so as to prevent interference with operator wiring

  • Add media

  • Heater/ Fan (If equipped)- The heater fan should be terminated properly and mounted so that it will not contact any wires in the operator cabinet. Ensure it is tested and functional. The thermostat should be set at 30° Celsius for the fan. Heater is self regulating

  • Motor brake- When the gate is not in motion, the brake should hold the gate in position. When the gate is in motion, the brake should have power and be released, allowing gate movement.

  • Photo eyes- When the photo eyes are blocked, the gate should react accordingly. Use the provided filters to simulate inclement weather when testing alignment

  • Sensing edge (If equipped)- the resistance should meter 8.1-8.7K. when squeezed the reading should drop to zero

  • Add media

  • Traffic lights (If equipped)- the traffic light(s) should be red unless both gate panels are fully open, in which case the light will change to green. If equipped, bi-directional traffic light logic must be verified

  • Add media

  • UPS (If equipped) ensure proper testing and functionality is observed per manufacturers instructions

  • Wiring- All wires should be properly seated in the terminals in the operator and column termination box and securely tightened. All wires should be left in a state of cleanliness and should be labeled as required by specifications. Do NoT substitute wire color

  • Add media

  • Gate limits- The gate limits should be adjusted so the gate panels, when in the fully closed position, are all parallel . When fully open, the gate panel bumpers should be within 1/2” of each other, but MUST NOT contact each other during normal operation

  • Mechanical
  • Access Door Locking- All doors should lock and unlock as designed

  • Top track (If applicable)- installed plum and level, all fasteners should be tightened to 90 ft/lbs with torque wrench

  • Add media

  • Columns- Should be level and plum, anchors tighten to approximately 210 ft/ lbs. Column base plates must be appropriately grouted

  • Add media

  • Drive pin- and sure all fasteners are tighten to 90 ft/lbs. verify the drive pin is not contacting column cover plate at any point

  • Add media

  • Guide roller wheel- ensure guide roller wheel assemblies level insecure, traveling in the middle of the top track assembly

  • Add media

  • Hinges- should be tightened to 85 ft/lbs, greased as needed. Do not over grease hinges

  • Through bolt large gear (If equipped)- Following the included instructions to drill a half inch hole through the large gear and spacer plate, ensure to bolt the large gear in place

  • Add media

Sign off

  • Wallace international is pleased to have supplied a speed gate automated gate for your facility. The product is expected to perform as designed providing basic maintenance is conducted on a regular basis. Maintenance required by the owner is detailed in the owners manual which was provided when the product was installed. Scheduled preventative maintenance is available through Wallace international, or a Wallace international approved installer.

  • By signing below, facility staff is/are acknowledging having attended the commissioning meeting upon completion of the installation. The meeting is held to a sure that they use, maintenance, and troubleshooting procedures for the product or understood by those responsible for the operation of the product. Signatures also indicate acknowledgment of receiving owners manual with copy of installation checklist and speed gate automated gate access keys.

Technician’s Recommendations

  • Comments

  • Completion time

Electronic Signature Acknowledgement-I agree that my Electronic signature is a Legally and Binding Equivalent to my handwritten signature. Whenever I execute an Electronic Signature, it has the same validity and meaning as my Handwritten Signature. I will not at ANY time in the future, REPUDIATE the meaning of my Electronic Signature or Claim that my Electronic Signature is not Legally Binding.

  • Wallace Perimeter Security Representative

  • Customer representative’s signature

Documents

  • F612C83A-2982-4841-A048-51ED6742F9F8.jpeg
  • C34239FC-5F55-4D49-A92C-393453C61C30.jpeg
  • 064EFD5A-AE74-428C-B89E-4BCBC146788A.jpeg
  • AACD8209-7712-4A29-8FB3-6C825F642D7C.jpeg
  • 6F438784-8DFC-4C47-8AA6-B44BF8CAA43F.jpeg
  • F5B5FCA8-6FCB-410C-A8AF-DB832F4AF7C0.jpeg
  • 4FC902E1-C606-4D0C-A4CD-A97A8CA76DB9.jpeg
  • B4D5F1C3-1627-483D-8F57-9716A691775B.jpeg
  • EB341A8C-14E4-4879-AA90-2961818EF4F7.jpeg
  • 7D2636DF-6CB8-4C85-B53C-1D69FDD79AD5.jpeg
  • 764944F6-9A3F-4E95-B163-0579187096CF.jpeg
  • F77C8A3B-588C-42AD-8789-3658FF12A16C.jpeg
  • 7F05F200-B8F4-466F-8279-8022BECF0A2C.jpeg
  • 9B52A475-F099-4B01-BE52-0AA1CE753554.jpeg
  • 56B7234D-84D0-41DC-9E1B-2D0E89E4FA15.jpeg
  • DB82D830-6EED-4DB1-8357-7BAC955FD1DB.jpeg
  • 639D0C2F-A365-467A-A71F-4B054C241EBF.jpeg
  • 3396B010-65D7-439F-85B0-25316F661FDF.jpeg
  • 9255AC66-13CC-4319-9051-10F026202B2E.jpeg
  • 00F44110-59DE-4E9C-A51A-1291C27CE35D.jpeg
  • 8366E73E-3A42-4E62-A3D3-52D1BD569883.jpeg
  • 0569164F-1609-4BA5-8AAE-22CD5424031E.jpeg
  • 85435C0A-6AB0-49F3-9CF3-4B9DF7506C0C.jpeg
  • EC3100D6-925F-4F6B-84A3-1A390E1DB599.jpeg
  • 5BAAC5E0-9915-42B4-955E-C76465FEFD24.jpeg
  • 653F0C8F-B91E-4F70-8572-F89914837258.jpeg
The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.