Window, door or other frame is to the standard and quality set out in the approved sample panel.
-
Window, door or other frame is to the standard and quality set out in the approved sample panel.
-
All restraints and other steel sundries are installed correctly .
-
All EDPM's and DPC's are installed correctly.
-
All horizontal and vertical EDPM's or DPCs are installed correctly and to specification.
-
Position of windows, doors or other frame types is correct to the required line, height and axle .
-
All window materials are in line with agreed manufacturers recommendations.
-
All openings are correct to current drawings and have been set to the height and position required.
-
All head and cill finishings have been completed and are in line with the site requirements and to the specification.
-
Are all heads, columns and other abutments of walls closed and sealed as per architects requirements.
-
All glass,subframe and frame surrounding elements have been sealed and installed.
-
All mastic sealing has been completed inner of outer as required.
-
DPCs are installed in the correct heights and positions.
-
Photos are available for this inspection or handover.
This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining Sub Contractors responsibility until practical completion has been achieved.
-