Audit Criteria

WHS Management Plan

  • Has the Plan been developed and authorised for the project?

  • Has the Plan been reviewed, at frequencies not exceeding 6 months?

  • Has the Plan been issued to Subcontractors at Tender stage and when updated?

  • Have changes to the Plan been communicated at WHSE Committee Meetings?

  • Have all members of the team signed onto the Plan?

Safety in Design

  • Are safety in design workshops held?

  • Are safety in design assessments completed and reflect requirements under the Regulations, such as Confined Spaces, HMT's, Hazardous Substances, etc.

  • Are the unresolved design issues transferred into the project risk register?

Risk Register & Workshops

  • Has the Risk Register been developed and is Site Specific?

  • Has the Register been reviewed at frequencies in accordance with the WHS Plan?

  • Does the Register unresolved risks from the Safety in Design process?

  • Are the controls in the register effective for the nature of the work?

Training & Competency

  • Have personnel performing HRCW produced applicable licenses for the works?

  • Have personnel completed nominated training in accordance with the competency framework?

  • Are subcontractors conducting training relevent to their work?

  • Have all nominated HSR's been trained?

Inductions

  • Have all workers been inducted?

  • Is the Induction reflective of current activities on site?

  • Are visitors being registered and accompanied by an inducted person?

  • Does the Induction advise that Legislation, Standards & Codes are available?

  • Does the Induction advise that the Plan is available to workers at their request?

Audits

  • Are subcontractor Audits Conducted?

  • Have identified corrective actions/NCR's been closed out?

Incident Management & Emergency Preparedness

  • Is the incident management process being followed

  • Have Incidents been investigated in accordance with the investigation process?

  • Have lessons learnt from incidents been shared with subcontractors?

  • Have corrective actions been implemented and closed out?

  • For injured workers, has the injury management process been followed?

  • Has an Emergency Management Plan been developed for the project?

  • Has the Emergency Management Plan been reviewed at least 6 monthly?

  • Have project specific emergency scenarios been identified and documented in the plan?

  • Have emergency processes been tested in accordance with the plan?

  • Is emergency equipment available, maintained and appropriate to the works?

  • Has an emergency response team been formed and trained?

  • Has an emergency response team been formed and trained?

Inspection, Testing & Monitoring

  • Are WHS Inspections conducted in accordance with KPI's?

  • Are Task Observations conducted in accordance with KPI's?

  • Is equipment calibrated in accordance with manufacturer's requirements?

  • Are WHSE Committee Inspections conducted?

  • Is plant & equipment inspected and serviced in accordance with manufacturer's requirements?

Consultation

  • Are daily prestarts conducted?

  • Are toolbox meetings conducted monthly as a minimum?

  • Has a WHSE Committee been formed and meet weekly?

  • Have HSR's been elected by their workgroup and formally recorded?

  • Has WHSQ been informed of current HSR contacts?

  • Has a workplace notice board been installed including all information required by the WHS Plan?

  • Is relevant documentation shared where appropriate; i.e. WHSE Committee Minutes, lessons learnt, Notices, etc.

SAFE WORK METHOD STATEMENTS

  • Are SWMS developed for High Risk Work

  • Has a SWMS review checklist been completed?

  • Is there evidence that workers have acknowledged the SWMS for their activities?

  • Are SWMS reviewed every 12 months or where there is a change to the work process, or after an incident?

  • Where observed, is work being conducted in accordance with the SWMS?

Site Establishment

  • Has an Occupational First Aider conducted a First Aid Assessment for room and provision requirements?

  • Are first aid kits restocked regularly?

  • Are adequate amounts of first aiders available (1:25)?

  • Is First Aid Signage erected including nominated first aiders?

  • Are adequate facilities provided for staff and workers; i.e. toilets, coolers, sheds, etc

  • Has perimeter fencing/hoarding been installed, is secure and stable, and designed?

  • Has a gantry been installed where required as per engineer design?

  • Is clear and defined access available including seperation of workers and vehicles?

  • Has mandatory signage been installed along the perimeter of site including PPE & QBCC signage?

  • Is access lighting installed for entry/exit where required?

  • Are no smoking signs displayed?

  • Are shaker grids/cleaning equipment where applicable available for vehicles prior to exit from site?

Access & Egress

  • Are access ways clean, unobstructed and clearly defined?

  • Is access lighting installed, tested and signed in accordance with AS3012?

  • Are emergency escape routes clearly defined?

  • Is there separation of people and plant where interaction occurs?

Silica Dust & Air Quality

  • Are controls implemented in accordance with Appendix 4 of the Silica Code?

  • Are monitoring activities conducted where appropriate to determine if WES are regularly exceeded?

  • Are controls captured in SWMS?

  • Is appropriate RPE utilised and fit tested?

  • Is health surveillance conducted where applicable?

Asbestos

  • Has an Asbestos Register been developed/provided where appropriate?

  • Has an Asbestos Control Plan been developed for licensed removal work?

  • Has the Regulator been notified of the removal work?

  • Have clearance certificates been issued by the licensed removalist, including records of waste transport dockets?

Confined Space

  • Has a confined space permit been developed and approved for the work?

  • Have all persons associated in the confined space activity been trained for their role?

  • Have SWMS been developed and approved for the activity, including emergency response arrangements?

Cranes

  • Has a third party engineer verified the commissioning and erection documentation?

  • Have the crane/s been serviced in accordance with manufacturers requirements?

  • Has the operator/s conducted familiarisation training?

  • Has a procedure been developed and implemeted for coordination of plant sharing air space with cranes?

  • Have lifting plans been developed for required activities such as tilt up/precast?

  • Have ground conditions been confirmed as adequate prior to outrigger setup?

  • Has cranesafe certificates been provided?

  • Is all lifting equipment inspected and identified as current?

Hazardous Substances/Dangerous Goods

  • Are SDS' and Risk Assessments readily available for DG/HS products?

  • Are DG/HS substances stored and seperated in accordance with the SDS?

  • Have workers been trained into the use, storage and disposal of these products as per the SDS and/or SWMS?

  • Are substances appropriately bunded or spill kits of the correct type available for the quantity stored?

  • Are containers appropriate to the substance and correctly labelled?

  • Is DG/HS signage displayed at the storage facility and emergency equipment available?

Demolition

  • Has a demolition plan been developed for the work?

  • Has WHSQ been notified prior to demolition work occurring?

  • Have services been identified and isolated prior to the work occuring?

  • Has a demolition permit been developed and approved prior to works occuring?

Electrical

  • Are switchboards and temporary construction wiring installed in accordance with AS3012?

  • Is access lighting in place, with emergency signs and battery backup drain test completed?

  • Has the electrical contractor maintained a register for electrical installations?

  • Are contractors inspecting, testing and maintaining electrical equipment?

Excavation

  • Are excavations greater than 1.5m benched, battered, shored or otherwise inspected by a geotechnical engineer?

  • Are open excavations inspected by a competent person?

  • Are excavation permits utilised and approved, including identification of any services?

  • Is safe access and egress provided for workers within the excavation?

  • Where shoring systems are used, has a geotechnical engineer approved the system for the intended loads of the excavation?

  • Has the excavation been secured from unauthorised access and potential falls by barricades, fencing, etc and signage?

  • Has the zone of influence of the excavation been considered regarding plant movement or material storage?

Falling Objects

  • Wherever possible, are perimeters encapsulated to prevent objects falling?

  • Are perimeters clean and clear of materials to prevent objects falling?

  • Are zones established and signed on open perimeters and penetrations to identify need for tool/equipment tethers, hard hat restraints, and other falling object controls?

  • Are exclusion zones established and maintained below areas where objects could reasonably fall?

  • Are hoardings installed to control falling objects as per Regulations?

  • Is perimeter containment screening installed and fully encapsulated to prevent objects falling as per the Regulations?

  • Are catch platforms installed and secure, with SWL identified on them if used as a working platform?

  • If adjoining areas/properties are excluded, has approval been sought?

  • Where gantries are installed, are they installed and protected as per Regulations?

  • Where materials are lifted, are they lifted in a way to prevent objects falling?

Fire Protection Systems

  • Are fire extinguishers available at egress points on each floor with signage displayed?

  • Are fire hydrants installed and charged when the building has reached an effective height of 12m, and within two floors of the deck under construction?

  • Are Hot Works Permits developed for activities that generate sparks, flash, etc.

  • Is task specific fire equipment available for hot works?

Formwork

  • Has a formwork plan been developed and approved by a competent person or RPEQ as required by the formwork code?

  • Are handover inspections completed prior to pour, with evidence of close out of issues raised by the engineer where appropriate?

  • Have inspections been completed pre and post jumping of screens and jumps?

  • Are penetrations protected and adequately covered?

  • Is adequate access provided to decks/jumps as per the formwork code?

  • Have emergency procedures been developed and tested for jumps?

  • Is a system of work developed and implemented for stripping; including verification to strip, exclusion zones, method of stripping, cleanup, etc?

  • Does the formwork process include effective management of falling objects?

Hazardous Manual Tasks

  • Has a Hazardous Manual Tasks Assessment been completed where HMT risks occur?

  • Has the safety in design risk assessment considered HMT risks?

  • Where observed, are HMT risks effective in practice or could an alternative way be conducted?

  • Are workers trained into Hazardous Manual Tasks risks?

Housekeeping

  • Are general areas clean and clear, with material stored in an orderly fashion?

  • Are adequate amounts of bins available and accessible?

  • Are contractors regularly cleaning their designated work areas progressively?

  • Are dust controls utilised for housekeeping activities?

Noise

  • Have noise assessments been conducted for plant/activites that may exceed designated thresholds?

  • Have appropriate noise control measures been documented and implemented; i.e. barriers, maintenance, seperation, signage, PPE

  • Have complaints for excessive noise been documented and resolved?

PPE

  • Are higher order controls available in lieu of PPE?

  • Have workers been trained in the use and maintenance of PPE?

  • Are workers wearing appropriate PPE for the task and is it in good condition?

  • Has Sunscreen been provided for workers?

  • Has height safety equipment been inspected by a height safety inspector at 6 month intervals?

  • Is appropriate PPE signage displayed?

Plant & Equipment

  • Are mobile plant checklists completed and verified for all powered mobile plant on site?

  • Is design/plant registration completed for appropriate plant; e.g. Cranes, pumps, hoists, etc.

  • Is there clear separation of people and plant?

  • Is signage displayed for mobile plant operating in areas?

  • Is plant operated by competent/licensed personnel?

  • Are certificates of calibration current for relevant equipment?

  • Are keys removed from plant at end of shift and plant stored safely?

  • Are mobile plant outrigger setup permits completed and approved prior to setup?

Precast

  • Has a certificate of compliance been completed for each panel including engineer inspections, concrete test results, etc

  • Have shop drawings been provided for each panel?

  • Has a designer approved the shop drawings, rigging configuration and bracing design if applicable?

  • Has a lift plan been developed for the installation of panels?

  • Are panels stored and secured as per design?

  • Has lifting equipment been inspected and tested?

  • Are secondary lifters utilised when lifting over people?

  • Is an effective system in place for lifting of panels; communication of activity, warning systems during lifting, defined movement and exclusion zones, etc.

  • Has an engineer approved the removal of braces where appropriate?

Scaffold

  • Have scaffold plans been developed and approved; including any designer, supplier or manufacturer's requirements?

  • Has the scaffold (including mobile and edge protection) been installed by competent or licensed persons?

  • Has fire retardent shadecloth been used?

  • Is the supporting structure/ground suitable for the scaffold loads?

  • Are handover certificates and monthly inspections completed?

  • Is the scaffold protected from impact of vehicles or plant?

  • Is a tie register in place and current, including torque wrench calibration?

  • Has the scaffold been installed as per the design, using a safe system of work?

Traffic Management

  • Has a Traffic Management Plan (TMP) been developed for the project; including internal traffic risks as well as external?

  • Have Traffic Guidance Schemes (TGS) been developed by a qualified person and approved by council and Qld Police?

  • Are permits current and reflective of the scope of works?

  • Are traffic controllers qualified and inducted into their roles and responsibilities?

  • Are daily signage checklists being completed?

  • Does the signage setup reflect the TGS requirements; where different has this been documented?

  • Is there evidence of regular traffic management inspections?

Work at Height

  • Are work at height activities conducted in accordance with the hierarchy of control? i.e. work from ground or solid construction, a fall prevention device, work in fall restraint, work in fall arrest.

  • Are platform ladders or other plant (scaffold, MEWP's) used in lieu of A frame ladders?

  • Are workers trained to conduct Work at Height acivities?

  • Is the over/under permit process implemented and effective?

  • Where works are conducted near perimeter edges and penetrations, are controls implemented to prevent persons and objects falling; such as tethers, exclusions for ladder work, exclusion zones, nets, etc?

  • Is a rescue plan in place for retrieval from heights?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.