QUALITY INSPECTION - PRE WINDOW INSTALLATION.
-
1. RAMS Available and Approved.
-
2. Window Specification and Drawings Approved.
-
3. Laydown areas off-loading agreed and available.
-
4. Access agreed and work faces available per programme.
-
5. Datum’s/Grids Available and recorded/ checked.
-
6. Additional Information.
QUALITY INSPECTION - WINDOW INSTALLATION.
-
7. Brkt location at glass support Locations.
-
8. Brkt fixing as specified. eg 2no Hilti HUS - 6 Torque 10Nm.
-
9. Brkt to concrete Packer Installed. (to reduce thermal bridging.) If specified.
-
10. Fixing centres/lugs as per drawings eg.150mm in then max 450mm centres.
-
11. Lug Fixings as per specification.
-
Page 2/5
-
12. Check fixings are capped off with sealant where necessary. ( Direct fix only )
-
13. Check that frame mitres and muntin joints are correctly sealed evidence of excess<br>sealant.
-
14. Glazing rebates are clean prior to fitting glazing/gaskets.
-
15. Inner air seal gaskets fitted correctly.
-
16. Glazing packers/supports to correct location & orientation.
-
17. Glazing units positioned centrally within rebate and correct size.
-
18. Beads secure with external gaskets (no excessive gaps.)
-
19. Drainage paths clear.
-
20. Check operation of opening vents check that any necessary adjustments have been<br>carried out.
-
21. Check compression on vent gaskets.
-
22. EPDM Interfacing substrate 50mm cover + terminate the edge of EPDM. Bond or mechanically fix to window.
-
23. Cill / Flashings Installed.
Page 3/5
-
24. Silicone/ Structural Mastic Complete.
-
25. Actuators/ Teleflex Fitted.
-
26. Keys provided.
-
27. Protection Installed If specified.
-
28. Additional Information.
-
29. Additional Information.