Main Contractor
-
Site
-
Location
-
Conducted on
-
Prepared by
-
Persons Carrying out work to Area being Accessed
DRAWINGS
-
Elevation Drawings - M. Clarke Drawings
PREPARATION FOR RAINSCREEN CLADDING - THERMOWOOD/TERRACOTTA ETC
-
Have the Operatives been provided with sufficient training in the specified system?
-
Has the operative been given the relevant drawings and details to complete the works?
-
Has the windows / curtain wall / doors been installed to the correct levels?
-
Are EPDM's correctly installed?
-
Is wall to correct line and level?
FLASHING / PODS / CILL CORNER TRIMS
-
Are cills, pods and flashings been installed to the correct design details? Thickness, colour and depth
-
Are cills, pods and flashings been installed using the fixings and centres?
-
Are cills, pods and flashings been installed to suit correct cladding set out and joints?
BREATHER MEMBRANE AND SUBFRAME SETTING OUT
-
Have all vents and rainwater pipes been taken through the substate?
-
Has correctly specified breather membrane been installed?
-
Has the breather membrane been dressed out and over horizontal flashings / pods and taped?
-
Has breather membrane been taped at vertical joints and taped 300mm at horizontal joints?
-
Has EPDM been installed to all vents / rwp's / louvre bracket fixing centres?
-
Is there 2nr brackets for any one rail minimum?
-
Have thermal pads been installed behind brackets?
-
Have correct type and number of fixings been used?
-
Have brackets been fixed at stud locations?
-
Have brackets been set in accordance with deflection point locations?
INSULATION / TAPING
-
Has insulation been fitted as tight as possible?
-
Has fire barriers been fitted and at correct locations?
-
Has all outlets, brackets, vents etc been taped up?
Inspection result
-
Result of the inspection
-
Site notes
-
Should you have any enquiries regarding this inspection report please contact M Clarke & Sons on 02825822500.
-
M. Clarke Representive
-
Main Contractors Representative