Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Have all team members carried out company/site induction and hold a white card?
-
Are all team members on site wearing the required PPE.
-
Have you referred to the applicable Proplumb SWMS?<br>
-
Does the SWMS cover all risks associated with the job to be undertaken? (if no complete risk assessment before proceeding)
Pre Start checks.
-
Are all footpaths, crossovers, sewer and stormwater pit lids free from damage and in good condition?
-
Are all permanent fences free from damage?
-
Are all of the set out pegs installed and free from damage?
-
Can the installation of sewer & stormwater drains proceed with no obstructions?
-
Are all concrete piers or screw piles free from the sewer & s/w runs?
-
Is the water tapping complete and in good condition?
-
Has the underground electrical been done?
-
Has the 1/4 minus or 7mm scoria been ordered?
-
If A/G drains are required have the 20mm scoria been measured and ordered?
-
Have you got sufficient pipe and material to complete the job?
-
Has the sewer/septic inspection been booked?
-
If any of the above are answered NO, must call the office immediately.
-
I have reviewed the appropriate SWMS and have assessed the site for any further hazards. I have completed this risk assessment to cover all other hazards involved and agree it is a fair assessment of the job and I authorize for this work to proceed.