Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Have you filled out the Proplumb Risk Assessment form?
Onsite Checks.
-
Is the site free from damage or vandalism?
-
Have you checked that the north arrow on the plan is correct?
-
Is the solar panels installed between 70deg West & 50deg east of north?
-
Will the solar panels be free from shade between 9am and 4pm?
-
Will the solar panels have a minimum inclination of 10 deg? (roof pitch)
-
Is the spouting free of dents and scratches where you have been working?
-
Have you installed the solar panels in the exact location on plan?
-
Has TOT/Mirror paste been used on all brass olive joints and tightened sufficiently?
-
Are all Z brackets tightened to rail and secured through panel?
-
Have you opened the bleed valve cap 2 full turns?
-
Has the correct armor flex been used on all flow and return lines?
-
Is the roof free of mud, debris, offcuts, etc?
-
Have you checked that all damaged roof tiles have been replaced and that the roof is watertight?
-
Is there any spare roof tiles left on site after you have replaced the damaged tiles?
-
Has the sensor wire been run and tied off to a roof truss to protect the terminal joint?
-
Are all armor flex lines strait, clipped and armor flex joins taped neatly with black duct tape?
-
Have you checked that the flow and return lines do not pass through a man hole or over an exhaust fan?
-
Is all pipework in tight against the frame and not bulging out into the cavity?
-
Have you positioned the flow and return lines out the wall in accordance to the manufacturers or particular builders requirements?
-
Are all flow and return lines clear of touching any plastic pipework or wiring?
-
Have you pressurised the the entire solar system including flow and return lines?
-
Have you drained the system after testing?
-
Has the UV rated armor flex been left long and taped back on its self to cover any sharp edges?
-
Has the sensor wire been ran out with the flow line and taped off in a bundle?
-
Has all rubbish been disposed of as per builders specific requirements?
-
The above information is true and correct.