Title Page

  • Site conducted

  • Audit Title

  • Project Name

  • Conducted on

  • Prepared by

  • Location
  • Instructions
    -------------------
    1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
    2. Add photos and notes by clicking on the paperclip icon.
    3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
    4. Complete audit by providing digital signature.
    5. Share your report by exporting as PDF, Word, Excel or Web Link

Kingspan FL

  • Main Contractor:

  • Project Number:

  • Issued to:

  • QA Sheet No:

  • Elevation:

  • Level:

  • Comments:

Metsec Framing

  • Metsec stud positions correct, lined and levelled within tolerance.

  • Personnel

  • Membrane installed.<br>

  • Personnel

Seals

  • Base support cleats installed in accordance with A2O drawings <br>

  • Personnel

  • Gaskets and seals installed in accordance with A2O drawings.<br><br>

  • Personnel

Panels

  • Check that panels are un-damaged as they are removed from pallets and that there is no significant colour variation. <br>

  • Personnel

  • Check panels are properly engaged into each other and horizontal joints aligned with adjacent panels. <br><br>

  • Personnel

  • Panels fixed to studs at head in accordance with A2O drawings. <br><br>

  • Personnel

  • Protective film to be removed from panel faces prior to installation (unless instructed otherwise by client). <br>

  • Personnel

  • All vertical gaps between panel joints to be fully packed with either loose rockwool (min 23kg/m3 density) or fire rated canister grade foam.<br>

  • Personnel

Flashings/Joint Gaskets

  • Vertical recessed top hat and insert installed in accordance with A2O drawings.<br><br>

  • Personnel

  • 9x3mm continuous butyl tape applied behind any face fix flashings. <br>

  • Personnel

  • Profiled butt straps present at flashing joints. <br>

  • Personnel

Completion

  • Installer Signature:

  • A2O Signature:

  • Client Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.