Information

  • Site conducted

  • Site Inspection Title:

  • Report Serial Number:

  • Client:

  • Conducted On:

  • Report Prepared By:

  • Site Address:
  • Contractors On Site:

WORK IN PROGRESS

  • The following works are currently in progress:

Site Office Set up

  • Has A2O board been displayed and in use?

  • Signing in and out sheet being used and up to date?

  • Daily site diary being completed and up to date?

  • Construction drawings and latest register available for inspection?

  • Fully up to date programme available for inspection?

PREVIOUS SITE INSPECTION

  • Has the site received a previous site inspection?

  • Has the Site Manager / Supervisor completed all weekly site safety site file documentation and issued it to A2O head office?

  • Have all previous site inspection non compliance actions been closed out?

  • Additional comments on the section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

TRAINING

  • Does the Site Manager / Supervisor hold SMSTS / SSSTS or other site management qualification?

  • Are all current operatives training cards suitable for tasks being carried out?

  • Are toolbox talks carried out weekly or more frequently if required?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

SECURITY

  • Are A2O works areas secure from unauthorised persons?

  • Are all A2O tools and plant secure on site?

  • Are A2O logo hi-vis vests being worn?

  • Additional comments on the section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

PERFORMANCE BEYOND COMPLIANCE

  • Are there any examples of innovation in health and safety management and best practice?

  • Is there any evidence of consulting with the workforce?

  • Additional comments on the section are:

  • Any non-compliance within this section of the audit will require urgent rectification..

INDUCTION

  • Are A2O inductions carried out?

  • Is the induction translated/explained to operatives who's English may not be as good as others and translated to them by someone who speaks their language within A2O?

  • Are site inductions available within the site safety files for all site operatives currently on site?

  • Are copies of training qualifications and cards available within the site safety file?

  • Additional comments on the section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

MAIN SITE SAFETY DISPLAY NOTICES

  • Are site rules displayed?

  • Has site displayed a hazard board with up to date hazards indicated?

  • Is there an emergency first aid notice displayed identifying site first aiders and contact numbers?

  • Is there a current Traffic Management / Logistics Plan in place?

  • Additional comments on the section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

MAIN SITE FIRE PLAN AND EMERGENCY PROCEDURES

  • Does site have fire extinguishers and fire call points located at regular intervals around site?

  • Are fire evacuation plans clearly displayed at each fire point on site?

  • Are all fire routes clearly signposted and clear from obstructions?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

ASBESTOS MANAGEMENT

  • Is an asbestos survey report / register / clearance certificate available?

  • Is a management procedure in place?

  • Is this covered in the site induction?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

RISK ASSESSMENTS

  • Is a current, suitable and sufficient risk assessment available for inspection on site?

  • Is A2O Copy of RAMS signed off by A2O manager?

  • Is A2O copy of RAMS signed off by a member of client management?

  • Is the current revision copy of A2O RAMS available on PIM?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

METHOD STATEMENTS

  • Is the Method Statement site specific and in line with all tasks to be undertaken?

  • Are they communicated to operatives and countersigned as confirmation of being understood?

  • Are site operations conducted in line with the method statement?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

COSHH

  • Have all harmful substances been identified on site?

  • Are hazardous substances properly stored and controls for safe use been put in place?

  • Are Material Safety Data Sheets and COSHH Assessments on site to accompany substances being used?<br>(It is not acceptable for a safety data sheet to be provided on its own to highlight COSHH risks, it must be supported by a COSHH assessment.

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

NOISE AND VIBRATION

  • Have noisy operations with a risk of exposure above 80dB been identified.

  • Is a system of monitoring and recording noisy works in place and being updated?

  • Has a requirement for noise exclusion zones been assessed and implemented if required?

  • Is hearing protection provided and being used correctly used?

  • Are appropriate control measures implemented?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

PERMITS TO WORK

  • Have activities requiring PTW been identified?

  • Are they retained on site?

  • Does a nominated person control hot works permits and are controls adequate?

  • Are Fire Extinguishers available for hot works?

  • Any non-compliance within this section of the audit will require urgent rectification.

PROTECTING THE PUBLIC / OTHER OPERATIVES

  • Is there segregation suitable and robust hoardings, barriers or fencing?

  • Is signage suitable and sufficient?

  • Is traffic management suitable and sufficient?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

MAIN SITE FIRST AID PROVISION

  • Have qualified first aiders been identified?

  • Are there adequate first aid provision and is it well stocked and clean?

  • Is there an accident book or accident report sheets on site?

  • Are all A2O accidents, near misses and incidents recorded?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

PERSONAL PROTECTIVE EQUIPMENT

  • Has suitable PPE been provided for activities being carried out?

  • Is the PPE being worn fit for purpose?

  • Is PPE in good condition?

  • Are appropriate dust masks being used for required tasks?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

SAFE PLACE OF WORK

  • Can the working area be reached safely trough general site areas?

  • Are site temporary and permanent structures stable?

  • Is housekeeping in good order and the site free from trip hazards?

  • Is the site compound and storage area in good order with waste and materials stored safely?

  • Is the working area / access adequately lit?

  • Have temperature and weather conditions been taken into considderation?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

LIFTING OPERATIONS AND LIFTING EQUIPMENT

  • Are operators / banksmen / slingers competent?

  • Is there an up to date LOLER register held on site?

  • Do completed contractor LOLER registers account for equipment on site, and are they completed weekly?

  • Does the lifting equipment have current inspection / test certificates?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

MANUAL HANDLING

  • Has a manual handling assessment been carried out and being adhered to?

  • Are alternative mechanical means utilised?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

LADDERS

  • Are ladders the right equipment for the job?

  • Has all other access equipment been considered?

  • Are ladders in good condition?

  • Are the correct size ladders being used?

  • Has client agreed to the use of ladders?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

SCAFFOLD ACCESS / ACCESS TOWER

  • Is scaffolding used on site?

  • Is Scaffold used for access to work zones only?

  • Are safety harnesses used during cladding works from the scaffold?

  • Are appropriate guard rails and toe boards in place?

  • If required, are brick guards / debris netting / debris fans installed and suitable?

  • Are platforms fully boarded?

  • Are materials evenly distributed?

  • Are platforms clean and free from debris?

  • Are loading bays designed and marked with loading limits?

  • Is scaffold inspected / tagged every 7 days, with reports held on site?

  • Are mobile towers / podiums in use and are they fit for purpose?

  • Are towers erected and inspected by PASMA trained personnel?

  • Is there a scaffold rescue plan in place?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

ROOFWORK

  • Is all roof access controlled by a permit to work?

  • Do A2O works require access to the roof only i.e. not actual roof works?

  • Is there suitable protection to prevent falls of persons / objects?

  • Are materials stored securely and safely, with tie down provisions made for strong wind conditions?

  • Are fragile roofs areas such as sky lights cordoned off to prevent falls?

  • Have 'safe zones' been created been created below fragile roofs?

  • Have adverse weather conditions been taken into consideration?

  • Are harnesses / lanyards utilised where required?

  • Are safety nets / crash bags or other fall protection systems used?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

EXCAVATIONS / GROUND CHECK

  • Are regular A2O ground check inspections being carried out and recorded?

  • Are further ground checks being undertaken following any changes to the ground e.g. adverse weather or heavy rainfall, backfilled excavations.

  • Have any existing excavations been taken into consideration in relation to their proximity to A2O MEWP access/work zones.?

  • Any non-compliance within this section of the audit will require urgent rectification.

POWERED ACCESS EQUIPMENT (MEWPS)

  • Is the equipment stable?

  • Are equipment operators trained and competent?

  • Is equipment being used in a safe manner?

  • Does the access equipment have a current inspection / test certificate?

  • Are daily plant inspections being carried out prior to using the plant?

  • Are machines parked against the structure in a way to allow easy and full access to the emergency ground lowering controls?

  • Is there an emergency MEWP rescue plan in place?

  • Has the emergency rescue plan been briefed to the operatives and signed.

  • Are operatives carrying out emergency lowering procedures on a weekly basis and recording.

  • Are work areas safe for operatives and others?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

PORTABLE PLANT AND MACHINERY

  • Is a fuel bowser located correctly? Is the fuel bowser lockable? Is a drip tray in place?

  • Is a PUWER register held on site?

  • Are completed contractor PUWER registers account for equipment on site?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

TRAFFIC AND VEHICLES

  • Are there separate vehicle / pedestrian routes which are suitable and sufficient?

  • Are there adequate precautions during the use of vehicles (e.g. reversing warnings, signage)?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

ELECTRICAL SAFETY

  • Is the PAT test register Available for inspection within the site safety file?

  • Is the supply a maximum of 110V?

  • Are trip devices / RCDs used where mains voltage is used?

  • Are cables and leads in good condition?

  • Are trailing cables protected / routed to prevent damage?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

WORK AREAS

  • Are works areas free from congested?

  • Are work activities being managed safely?

  • Are suitable dust control measures in place, (I.e. dampening down during sweeping, dust extractor fitted to cutting equipment)?

  • Is there adequate storage facilities for materials?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

ENVIRONMENTAL

  • Is waste appropriately segregated on site?

  • Are spill kits in place?

  • Additional comments on this section are:

  • Any non-compliance within this section of the audit will require urgent rectification.

Report Summary

Report Summary

  • Site Inspector

  • Site Inspectors Comments

  • Site Manager / Representative

  • Site Manager / Representative Comments

COMPLETION ON NON-COMPLIANCES

  • The Site Manager is confirm that the non-compliances raised have been appropriately dealt within the time frame specified by: 1. Signing and writing the date next to the non-compliance item. THE COMPLETED AUDIT IS TO BE RETURNED TO THE OFFICE FOR REVIEW AND ARCHIVE WITH PROJECT FILES

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.