Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
-
Instructions
-------------------
1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
TI Brick Slip
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
TI Brick Slip
-
Module end handed over to A2O by Caddick Construction<br> - Area to free of other trades
-
Personnel
- Installer
- A2O
-
Ensure the drip flashing is installed, with a maximum of 300mm centres between Tapcon fixings
-
Personnel
- Installer
- A2O
-
Ensure the top hats are level/plumb and correct to the drawings, with 600mm centres between top hats
-
Personnel
- Installer
- A2O
-
Ensure the top hat fixings are at 300mm centres between Tek Screw fixings.
-
Personnel
- Installer
- A2O
Hold point sign off
-
A2O manager
-
Ensure the cassette trays are installed level and to construction drawings.
-
Personnel
- Installer
- A2O
-
Ensure the cassette trays have 3 tek fixings aligned vertically at each interface with the vertical top hats, with the fixings catching both flanges on the overlap areas.
-
Personnel
- Installer
- A2O
Hold point sign off
-
A2O manager
-
Ensure the bricks are secure and seated correctly onto the cassette tray.
-
Personnel
- Installer
- A2O
-
Ensure the bricks are the correct colour as per drawing locations.
-
Personnel
- Installer
- A2O
-
Ensure bricks are free from damage and ready to handover.
-
Personnel
- Installer
- A2O
Completion
-
Installer Signature:
-
A2O Signature:
-
Client Signature: