Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
-
Instructions
-------------------
1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
Siderise Firebarrier
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
Siderise fire barrier materials
-
Fire barrier schedule is available<br>within the site documentation
-
Personnel
- Installer
- A2O
-
Fire barrier materials have been<br>checked on delivery to site to be<br>correct type and specification in<br>accordance with the A2O fire barrier<br>schedule
-
Personnel
-
Fire barrier materials have been<br>stored on site in an appropriate<br>manned in accordance with<br>manufacturers recommendation.<br>"Keep material in original packaging<br>until it is to be used. Store material<br>to protect against<br>damage including the weather"
-
Personnel
-
All fire barrier brackets, fixings and<br>tape has been delivered to site and<br>checked that they are in accordance<br>with the A2O fire barrier schedule<br>and manufacturers specification.
-
Personnel
Pre-installation
-
A site meeting with fire barrier<br>supplier [Siderise] arranged and<br>carried out in advance of installation<br>works commencing. To include any<br>training that may be required.
-
Personnel
- Installer
- A2O
-
A2O Fire barrier construction<br>drawing are on site within the A2O<br>drawing file.
-
Personnel
- Installer
- A2O
-
All installation operatives have been<br>briefed on the specific installation of<br>the fire barriers to be installed, in<br>accordance with manufacturers<br>recommendation
-
Personnel
Vertical barrier installation
-
Check fire barrier locations are in<br>accordance with A2O fire barrier<br>setting out construction drawings.
-
Personnel
- Installer
- A2O
-
At each fire barrier location, check<br>that thickness of fire barrier is in<br>accordance with cavity void plus<br>compression allowance in<br>accordance with the manufacturers<br>specification.
-
Personnel
- Installer
- A2O
-
If the fire barrier to be installed<br>requires to be cut to size, make sure<br>that the cut allows for the extra size<br>to ensure the required compression<br>and be sure to cut in the direction<br>that is marked on the foil facing to<br>maintain compression in accordance<br>with manufacturers specification.
-
Personnel
- Installer
- A2O
-
Manually fold the installation<br>brackets to allow the correct<br>embedment into the fire barrier. This<br>needs to be 75% of the depth of the<br>fire bracket to ensure a compression<br>zone within each barrier, i.e. if the<br>cut fire barrier is 100mm, the bracket<br>would penetrate the barrier 75mm.
-
Personnel
- Installer
- A2O
-
Bracket fixings are fixed at 600mm<br>centres with non combustible fixings<br>[no plastic or rubber washers].<br>Ensure fixings are as per A2O or<br>manufacturers specification.
-
Personnel
- Installer
- A2O
-
Ensure that the fire barrier is tightly<br>abutted to the barriers to each side<br>and seal the joints with RFT 120 x 45<br>foil tape.
-
Personnel
- Installer
- A2O
Horizontal barrier installation
-
Ensure that horizontal barriers are<br>installed after vertical barriers.
-
Personnel
- Installer
- A2O
-
Check fire barrier locations are in<br>accordance with A2O fire barrier<br>setting out construction drawings.
-
Personnel
- Installer
- A2O
-
At each fire barrier location, check<br>that thickness of fire barrier is in<br>accordance with cavity void and<br>allow a 25mm air flow gap between<br>the fire barrier front edge and the<br>rear face of the cladding panel. in<br>accordance with the manufacturers<br>specification.
-
Personnel
- Installer
- A2O
-
If the horizontal fire barrier to be<br>installed requires to be cut to size,<br>make sure that you cut the rear<br>edge of the barrier in accordance<br>with manufacturers specification.
-
Personnel
- Installer
- A2O
-
Manually fold RH installation<br>brackets 90 degrees at a point to<br>allow the correct embedment into<br>the fire barrier. This needs to be<br>long enough to allow the split end of<br>the bracket to protrude from the<br>barrier front face.
-
Personnel
- Installer
- A2O
-
RH Bracket fixings are fixed at<br>400mm centres with non<br>combustible fixings [no plastic or<br>rubber washers]. Ensure fixings are<br>as per A2O and manufacturers<br>specification. [3 x brackets per<br>1200m barrier length]
-
Personnel
- Installer
- A2O
-
Ensure that the fire barrier is tightly<br>abutted to the barriers to each side<br>and seal the joints with RFT 120 x 45<br>foil tape.
-
Personnel
- Installer
- A2O
-
Arrange inspection by Siderise before commencing with any further cladding finishes.
-
On completion of inspection, cavity<br>fire barriers are to be signed off by a<br>Siderise approved qualified person.
Completion
-
Installer Signature:
-
A2O Signature:
-
Client Signature: