INSPECTION CHECKLIST
-
Operating and emergency controls are in proper working condition, EMO button or Emergency Stop Device
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Functional upper drive control interlock (i.e. foot pedal, spring lock, or two hand controls)
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Emergency Lowering function operates properly
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Lower operating controls successfully override the upper controls
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Both upper and lower controls are adequately protected from inadvertent operation.
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Control panel is clean & all buttons/switches are clearly visible (no paint over spray, etc.)
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
All switch & mechanical guards are in good condition and properly installed
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
All Safety Indicator lights work
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Drive controls function properly & accurately labeled (up, down, right, left, forward, back)
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Motion alarms are functional
-
undefined
-
Safety decals are in place and readable
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Guardrails and anchor points are in place, and in good condition
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Work platform & extension slides are clean, dry, & clear of debris
-
undefined
-
Work platform extension slides in and out freely with safety locking pins in place to lock setting on models with extension platforms.
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Inspect for defects such as cracked welds, fuel leaks, hydraulic leaks, damaged control cables or wire harness, etc.
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Tires and wheels are in good condition, with adequate air pressure if pneumatic
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Braking devices are operating properly
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
The manufacturer's operations manual is stored on AWP (in all languages of the operators)
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Oil level, Hydraulic Oil Level, Fuel Level, Coolant Level
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Battery Charge
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
-
Outriggers in place or functioning. Associated alarms working
-
If "Fail" STOP WORK and report Issues to Data Center M&E Lead
Safety Precautions (Have, Look For, or be Aware of)
-
Personal Fall Arrest and Protective Equipment. (Harness, lanyard, hardhat etc.)
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
In windy conditions see manufacturer guidelines or if not in guidelines then if lift begins to rock in the wind lower the lift
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
Floor conditions: Drop offs, holes, uneven surfaces, and sloped floors.
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
Housekeeping: Debris, floor obstructions, cords, construction material and supplies.
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
Electrical power cables or panels, (minimum 10 feet away). If larger lines or wet conditions contact EH&S or the Electrical shop for guidance. Insolated small lines in dry conditions 3 feet away.
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
Chemical lines, gas lines, drain lines, and utilities.
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
Overhead obstructions
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
Loads (do not exceed capacity)
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
Watch for vehicular and pedestrian traffic. Set up barricades if necessary.
-
If "At Risk" STOP WORK and report Issues to Data Center M&E Lead
-
IF THE AERIAL LIFT FAILS ANY PART OF THIS INSPECTION, REMOVE THE KEY AND REPORT THE PROBLEM TO YOUR M&E LEAD AND DATA CENTER MANAGER. DO NOT ATTEMPT TO MAKE REPAIRS. ALL SERVICE IS TO BE CONDUCTED BY CERTIFIED VENDORS. IF ANYTHING HAS BEEN JERRY-RIGGED NOTIFY YOUR SUPERVISOR AT ONCE.
Inspector Sign Off
-
Add signature