Title Page

  • Conducted on

DETAILS

  • Client / Site: Barwon Water - Black Rock WRP Inlet Works Upgrade 400 Black Rock Connewarre

  • Inspection Area:

  • Reference: BW Technical Specification Rev 0 Clause: 38.6 Underground Services 38.7 Cable Pits 38.8 Underground Cable Routes 38.10 Conduits - General 38.15 Underground Conduit Installation

  • Document No. CA-CS-007 ITP No:

VISUAL CHECKLIST

  • Excavation clear of sharp objects

  • Provide polypropylene draw cords in all conduits including those with cabling installed

  • Seal spare ducts or conduits immediately after installation with a pliable non setting waterproof compound

  • Under roadways and areas subject to traffic movement, install cables in a duct or conduit extending to not less than 1mt on either side of the sealed surface or trafficable area and encase in concrete having a minimum cover thickness of 100mm

  • Moulded Fibre Cement Pit - minimum size: Internal dimension - 650 X 350 X 900mm deep unless otherwise specified

  • Provide each pit with a drain hole in the base positioned to drain into a drainage pit

  • Route markers placed at intervals of not more than 10mt for straight distances and at joints, route junctions, changes of direction,terminations and entry points to buildings

  • Marker plate flush in a 200mm minimum diameter concrete base, not less than 200mm deep

  • Underground cabling in Orange HD unplasticzed poly vinyl chloride (HDPVC) type conduits

  • Draw-in boxes shall be used where necessary to enable draw in for long runs of cables and shall not exceed spacing of 20mt

  • Conduit correct size for cable as per AS3000

  • Segregation between power and instrument wiring maintained

  • Marker tape shall be used positioned at approximately 50% of the depth of cover above the wiring system or any additional mechanical protection provided for the system

  • Provide clean sharp sand around cables and conduits installed underground

  • Seal conduits after the cable installation with pliable non setting waterproof compound

  • Standard Pit - Reinforced concrete with a minimum 150mm walls and 150mm base and complete with light duty gatic cover<br><br>Note* Incorporate an additive or concrete to prevent the ingress of water

  • Mould the word ELECTRIC into the lid for use on any pit containing electrical power cables

  • Provide a drainage pit filled with rubble, graded away from each cable pit, Min size 600 wide X 600 deep

  • Mark the direction of the cable run by marker plate direction indicators<br><br>Provide four distinctive versions of the marker plate containing single, through, L and T arrows with the latter three containing a centre marking <br><br>A group of two or more plates may be required at some route junctions

  • Marker flush to the surface in footpaths, roadways,paved areas, etc, and protruding 25mm above all other surfaces

  • Minimum spare space capacity of 50% for future additions

  • Conduits entering sewerage wet wells shall be sealed at the switchboard end after installation of the cables to prevent sewerage gases from entering the switchboard enclosure

  • Conduit fittings sized so that cable is not bent to less than its minimum bending radius

  • All burrs removed and screwed bushes fitted to ends

  • Notes/Comments

APPROVALS

  • Conduit system is

  • Actions to be taken:

  • Entered on Punch List

  • Punch list Reference Number:

  • Item No:

  • Person Completing the Checklist

  • Signature:

  • Agfab Approval By:

  • Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.