Title Page
-
Conducted on
DETAILS
-
Client / Site: Barwon Water - Black Rock WRP Inlet Works Upgrade 400 Black Rock Connewarre
-
Inspection Area:
-
Reference: BW Technical Specification Rev 0 Clause:
-
Document No. CA-CS-0????????????? ITP No:
VISUAL CHECKLIST
-
Mechanical installation complete (Check QA tag)
-
Correct motor size as per IFC drawings
-
Motor name plate details recorded
-
Guards are correctly fitted
-
All stopping plugs and bolts are in position and tight
-
There is no damage to the motor or cabling
-
Thermistor terminals segregated form power terminals
-
All seal are satisfactory
-
The electrical protection is correct
-
Electrical connection are tight
-
Earthing is satisfactory
-
No corrosion / IP56
-
Motors and / or fans are not rubbing against any object or housing
-
Visual inspection
-
Swivel poles can rotate freely without impacting adjacent equipment
-
Asset and cable labels installed and correct as per drawing
-
All switches installed and ready for energisation
-
Notes/Comments
APPROVALS
-
Motor Inspection is
-
Actions to be taken:
-
Entered on Punch List
-
Punch list Reference Number:
-
Item No:
-
Person Completing the Checklist
- Greg Grima
- John Toner
- Shane Dando
- David Howard
-
Signature:
-
Agfab Approval By:
- Greg Grima
- John Toner
- Shane Dando
- David Howard
-
Signature: