Project title Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Who is responsible for H&S on site
-
Location of local A&E
-
Project dates
-
CDM structure - Cleint, Principle contractor, Principle designer
-
How will be project information be communicated
-
Who are the nominated first aiders
-
Site rules
- 5 point PPE to be worn at all times
- No smoking
- All operatives to have a site induction before work
- No access to childen
- No unauthorised access
Pre start Risk assesment
-
Are there any obvious physical hazards that may affect the operatives on site? E.g.exposed wiring, loose fittings, damaged pathways...
-
Are there any environmental issues on site that affect the operatives?
-
undefined
-
Select any high risk activity
- Banksman to direct all traffic
- parking off site
- No reversing without banksman
- Agreed timed deliveries only
- No vehicles left running or un-supervised
-
Has an asbestos survey been carried out that relfects the project work location
-
undefined
-
Are there any unsafe areas the operatives must access or pass through to complete their work?
-
Select how traffic is to be managed
- Banksman to direct all traffic
- parking off site
- No reversing without banksman
- Agreed timed deliveries only
- No vehicles left running or un-supervised
-
Have all operatives received manual handling training
-
Can the public frequent the contract at anytime?
-
undefined
-
Is there adequate lighting on site whilst working?
-
Will operatives be working outdoors?
-
Is there a site evacuation procedure that has been communicated to all operatives
-
Is there storage on site?
-
Will work activity create dust if so how will this be managed
-
undefined
-
Have all operatives competencies been obtained and suitable for work type
-
Is the waste disposal process in place for the project
-
Are fire escapes clearly marked, free from obstacles, and emergency lighting in place where ever required?
-
Is there a first aider on site and access to a fully Stocked first aid kit
-
Is there working at height and how will this be managed
-
How is welfare being provided for site operatives
-
How is secuirty being managed
-
What are the fire and emergency procedures
- Banksman to direct all traffic
- parking off site
- No reversing without banksman
- Agreed timed deliveries only
- No vehicles left running or un-supervised
-
Materials requiring particular precautions
-
Other futher details