Title Page

  • Site conducted

  • Conducted On

  • Conducted By

  • Location
  • Scoring Criteria
    Compliant – No shortfalls identified, criteria met or standards required achieved
    Partially Compliant – Minor shortfalls identified in the standard or requirement, minor opportunities for improvement identified and the standard is still to an acceptable level. (For Example -PAT Testing – Most items tested and in date however a few units have been missed)
    Non-Compliant – The standard or requirement has not been achieved and deemed to be unacceptable. Immediate action is required to address the shortfall/s (Example – PAT Testing – Most items out of date and not tested)

Access, Fencing & General Site Arrangements

  • Fencing & Gates Complete and secure and in good condition

  • Gates Locks and Access arrangements in place (i.e. Contractor Access & Farmer Access)

  • Signage on Fencing and Gates (I.e. Emergency Contact Details and Access Details)

  • Fences earthed

  • Condition of grating & grating support

  • General Outdoor Lighting in Place and Operational

  • Road condition on site acceptable & Approach road (Has construction caused any issues)

  • Kerb condition

  • EV Charging in place and Operational

  • Parking provisions

  • Walkway condition (STF Hazards / Uneven)

  • Site Drainage system operational – review drains / channels for standing water

  • Construction Materials Removed / General Housekeeping Acceptable

  • CCTV in place and operational

  • Walfare facilities avaialble (i.e. Toilet) If No, are arrangments in place for when individuals are working on site (i.e Portable Toilet)

Environmental

  • Spill Kits available

  • Waste bins provided

  • Waste management contractor in place

  • Foliage / Weeding / Grass managed

  • Bunds Secure / Contained and in good condition

  • Bund drain valves in place and in correct position

  • Bunds not filled with fluid / rain water or foliage

  • Hazards to livestock considered

External Structures

  • General condition (paint, cleanliness around/under)

  • Fixings (if applicable, Guttering, Vents Etc

  • Doors closed

  • Door locks in place

  • Management of locks – suited keys in place

  • Earth points

  • Cable entry sealing / glanding

  • Air conditioning system condition (doors closed)

  • Button box (external fire system in auto, labelling of buttons within / EStops)

  • Deflagration panel – in place not rusty

  • Cable clamps in place

  • Signage in place on buildings / doors

  • Condition of bolts / floor fixings / handrails condition (Not Rusting, in good condition)

Foundations / Civils

  • Shuttering and Steelwork installed correctly Visual Check

  • Foundations finish correct

  • No chips or breakages on concrete

  • Membrane installed under stone

  • Stone finish completed

  • All ducts installed

  • Shims installed

  • Container corner clamps installed and bolted down (If Applicable)

  • Retaining wall installed

  • GRP / Grating clamped down and Even

Inverters

  • Earthing

  • Plastic covers removed (general transportation wrap)

  • Labelling in place

  • External condition

  • Doors closed & locked

  • Interlock keys in place on rings

  • DC cable entry glanding

  • Entry labelling

  • AC cable exit glanding

  • Exit labelling

  • Xcable

  • Livestock protection in place

HV Room

  • Access restricted and access arrangements in place

  • Lighting in place

  • Fire Exit Signage in Place and Operational

  • Fire extinguisher in place and correct type

  • Rescue hook available

  • First aid poster in place

  • Labelling in place

  • Interlocking

  • Interlocking explanations

  • Odours

  • HVAC Operational

  • Leftover isolation or lockouts removed

  • Fire system in place and showing no faults

  • Dust covers removed from detectors

  • Switchgear in good condition

Control room

  • Access restrcited and access arrangments in place

  • External condition

  • Internal cleanliness (Construction Material Removed)

  • Fire system in place and showing no faults

  • Dust covers removed from detectors

  • Lighting in place

  • First aid kit avaiable

  • Defib Available

  • Fire Exit Signage in Place and Operational

  • Fire extinguisher in place and correct type

  • Rescue hook available

  • First aid poster in place

  • HASWA Poster mounted with contact details provided (If Applicable)

  • Labelling in place

  • Interlocking

  • Interlocking diagramme

  • Odours

  • Telecomms in place and operational (Fibre / Phone / Satelite)

  • HVAC Operational

  • Leftover isolation or lockouts

  • Key box

  • SCADA system operational

  • SCADA Screen operating

  • Cabinet security

Transformers (TX)

  • Is the access to the HV TX interlocked back to the switchgear?

  • Does the Oil Transformer have a Bund and correct Oil Interceptor fitted?

  • Does the transformer have any signs of corrosion / Damage / leaks?

  • Does the TX have the correct warning labels attached (DOD/ HV)

  • Does the TX earthing look in good condition and clearly identified?

Meter room

  • Access restrcited and access arrangments in place

  • External condition

  • Internal cleanliness (Construction Material Removed)

  • Fire system in place and showing no faults

  • Dust covers removed from detectors

  • Lighting in place

  • First aid kit avaiable

  • Fire Exit Signage in Place and Operational

  • Defib Available

  • Fire extinguisher in place and correct type

  • Rescue hook available

  • First aid poster in place

  • HASWA Poster mounted with contact details provided (If Applicable)

  • Labelling in place

  • Interlocking

  • Interlocking diagramme

  • Odours

  • Telecomms in place and operational (Fibre / Phone / Satelite)

  • HVAC Operational

  • Metering seals in place and intact

  • UPS status / warnings

  • Vermin Screens to louvres in place

  • Basement condition

  • Any special access requirements to consider Confined Space

Solar Specific Considerations

  • Panels in good condition and clean

  • Mounting structure in good condition (No signs of corrosion / deformation)

  • Cables protected from livestock

  • Foliage / grazing managed around panels and arrangements in place to continually manage (Also confirm how this will be done Safely without damaging equipment)

  • Temperature Sensors in correct position (Middle of the Panel)

  • Angle of the pyranometers in-line with angle of panels

  • Roof top Specific - Edge protection in place (Fall arrest system in place etc...)

  • Roof Top Specific - Fragile surfaces protected and signed (i.e. Skylights)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.