Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
MAIN CONTRACTOR:
-
PROJECT NUMBER:
-
QA SHEET NO:
-
ELEVATION/ LOCATION:
-
LEVEL:
-
COMMENTS:
-
DUOSLAB BOARDS ARE INSTALLED TO THE CORRECT ORIENTATION WITH WEATHERPROOF FACE TO OUTSIDE AND BRANDING READ HORIZONTALLY
-
CORRECT FIXINGS HAVE BEEN USED TO FIX DUOSLAB BACK TO SUBSTRATE AND ARE INSTALLED AS PER MANUFACTURERS RECOMMENDATIONS
-
DUOSLAB FIXINGS HAVE BEEN INSTALLED WITH NYLON/ STAINLESS STEEL WASHER LAYOUT AS PER MANUFACTURERS RECOMMENDATIONS
-
DUOSLAB BOARDS HAVE BEEN INSTALLED WITH THE REQUIRED STAGGERED LAYOUT
-
DUOSLAB BOARDS ARE INSTALLED SNUGLY ABUTTED TO VERTICAL AND HORIZONTAL FIREBREAKS WITH NO GAPS
-
A2O PROJECT MANAGER
-
CLIENT SITE MANAGER