Information

  • Document No.

  • Contractor Name

  • Date and Time

  • Name of person completing this report

  • Location
  • Project / Site Name (i.e HUL117)

General

Quality Audit

Cable and splice works

  • Has the correct track been installed as per the design?

  • Has the correct sub duct been installed?

  • Has the correct cable been installed?

  • Has the tail into the FAT / FDT been taped correctly and cables routed around the box?

  • Have the FAT / FDT cables been labled correctly?

  • Has the FAT / FDT been labeled correctly?

  • Has the FAT / FDT been mounted to a mobra?

  • What is the overall quality of the works like?

Boxes

  • Is the box in at the correct depth?

  • Does the box have the correct flooring down?

  • Are all duct entry's into the box cut flush and bur free?

  • Has the mobra arm been fitted correctly?

  • Is the box free from debris and rubbish?

  • What is the overall box quality?

Toby Boxes

  • Is the correctly branded toby box in place?

  • Is the top of the toby level with the surface?

  • Is the toby free from obstruction?

  • Is the toby box located correctly in relation to the property?

  • What is the overall quality of the toby box?

General Comments

  • Any further comments or recommendations arising from this inspection?

  • Add relevant site photos (please include as many as possible)

Sign Off

  • Name & Signature of MS3 Supervisor

  • Name & Signature of Site Supervisor / Foreman

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.