Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Commissioning Survey
-
Has the charging equipment been installed in an optimum location with respect to the intended vehicle parking position?
-
Has the EV charging equipment been installed in a location to minimize the likelihood of vehicle impact damage?
-
If required, have protective barriers been provided?
-
Are the main operating controls and any sockets-outlets between 0.75m and 1.2m above the ground, and displays between 1.2m and 1.4m above ground?
-
Is there sufficient space around the charging equipment to open all doors and covers?
-
Is there sufficient space around the charging equipment for ventilation and cooling purposes?
-
Have all trip hazards been considered and , where possible, avoided?
-
Have any BS 1363 socket-outlets been labelled as electric vehicle connecting points?
-
Have pre-cautions been taken to prevent inadvertent energizing?
-
Inspections carried out as per BS 7671 Schedule of Inspections
-
Dead tests carried out as required by BS 7671 prior to energizing and appropriate parts of the test schedule completed.
-
Remaining tests carried out as required by BS 7671 after energizing and appropriate parts of the test schedule completed.
-
Correct operation of the charging equipment demonstrated to customer.
Electrical Checks
-
Number of phases
-
What is the maximum demand of the premises? (Amps)
-
Is the incoming supply metered?
-
What is the incoming supply?
-
Is the existing supply adequate for the additional demand?
-
What it the premises cut-out rating?
-
What is the earthing arrangement if the power supply?
- TN-C-S (PME)
- TT (Direct)
- TN-S (SNE)
- Customer substation (HV CT Metered)
-
Are the existing earthing arrangements compliant with BS 7671 as amended?
-
Is the service looped?
Installation Photos
-
EV charger installed
-
EV charger serial number
-
EV charger working
-
EV charger connection
-
EV charger location
-
EV charger isolation switch
-
Fuse board
-
Cutting loop
-
Electric Meter
-
Earthing arrangement
Completed by
-
Commissioning Date
-
Engineer Signature