Information

  • Site

  • Location
  • Conducted on

  • Prepared by

  • Personnel present

Administrative Requirements

  • Local authority approval in place for demolition I.e. Building licence, Demolition licence?

  • Add media

  • Has Worksafe been notified of the intention to carry out (Class1, 2 or 3) demolition work at least 5 working days before commencement?

  • Add media

  • Permit system in place for demolition?

  • Add media

  • Are contractors licenced to carry out demolition work?

  • Add media

  • Have they the correct licence class?

  • Add media

  • Is there a demolition plan with a methodology in place?

  • Add media

  • If structural stability is likely to be affected has the demolition plan been developed by a suitably qualified person E.g. Structural engineer or demolition rigger?

  • Add media

  • Have task and site specific JSAs been developed for demolition works?

  • Add media

General

  • Is good housekeeping maintained?

  • Add media

  • Debris and rubble cleared away regularly? Rubbish disposed of regularly?

  • Add media

  • Trip hazards identified and made safe?

  • Add media

  • All electrical equipment tested within 3 months and tagged?

  • Add media

  • Is an electrical register in place?

  • Add media

  • All electrical leads suspended with enough clearance for personnel and plant operating in the area?

  • Add media

  • Is appropriate PPE available and is it being used?

  • Add media

Utilities

  • Have all utilities/services been identified via as-con drawings or scanning reports?

  • Add media

  • Are these scanning reports/drawings attached to demolition permits?

  • Add media

  • Have all services within demolition area been isolated, removed or made safe?

  • Add media

  • Has an isolation permit been completed?

  • Add media

  • Do all isolated services have LOTO procedures in place?

  • Add media

Hazardous Materials

  • Has a hazardous material register for the building been requested from client and reviewed?

  • Add media

  • Has the hazardous material register review been noted within the Project Risk Register and Project Risk Assessment?

  • Add media

  • If friable asbestos or more than 10m2 non-friable asbestos is being removed, has the contractor got the appropriate licence?

  • Add media

  • Has the removal contractor an appropriately trained and licensed supervisor onsite coordinating removal works?

  • Add media

  • Has an asbestos removal control plan which is in accordance with Part 8.1 NOHSC 2002 been developed and implemented? <br><br>

  • Add media

  • Is a copy available on site?

  • Add media

  • Has asbestos removal been included in the Risk Register and Project Risk Assessment?

  • Add media

  • Has a task/site specific JSA been developed for asbestos removal?

  • Add media

  • Have appropriate signage and barriers been erected to identify asbestos removal exclusion zone in accordance with Part 9.2 of NOHSC 2002?

  • Add media

  • Is there sufficient and appropriate protective clothing and respirators available in accordance with Part 9.7 of NOHSC 2002?

  • Add media

  • If removing friable asbestos has air monitoring been implemented by an independent occupational hygienist?

  • Add media

  • Are any results of air monitoring available onsite?

  • Add media

  • Are the results communicated to workers?

  • Add media

  • If so how?

  • Are the results below national exposure levels (0.01 fibres/ml)?

  • Add media

  • Has clearance certificate been issued before other demolition works in that area have begun?

  • Add media

Fire Services

  • Has fire protection equipment such as hose reels been maintained where possible?

  • Add media

  • If not have additional fire protection methods been implemented such as fire extinguishers?

  • Add media

Public Protection and Surrounding Environment

  • Is demolition site securely fenced off or barricaded from public access

  • Add media

  • If applicable has scaffold been sheeted and have scaffold decks been carpeted to prevent debris falling below

  • Add media

  • Have gantries been installed over public footpaths

  • Add media

  • Has protection been provided for buildings in close proximity to the demolition site

  • Add media

  • Are vibration and noise levels being monitored?

  • Add media

  • Are they within acceptable levels?

  • Dust control and suppression methods in place?

  • Add media

Structural Stability

  • Is demolition work being carried out in a safe and logical sequence so as not to effect structural stability of the building?

  • Add media

  • Has loading capacity of floors been considered before placing machinery or loading building rubble on them?

  • Add media

  • Have any propping systems been designed/certified by a structural engineer?

  • Add media

  • Are propping systems inspected/monitored regularly?

  • Add media

Working at Heights

  • Are all penetrations or live edges where someone could fall 2m or more, barricaded with full edge protection or covered in accordance with OSH Regulations (WA) 1996, Reg. 3.54?

  • Add media

  • Where live edges exist and not barricaded, are fall prevention or fall arrest systems used?

  • Add media

  • Are all harness, lanyards, etc in good condition?

  • Add media

  • Are all harness, lanyards, etc recorded on a register?

  • Add media

  • Have all anchor points a safe load capacity of at least 1.5 tonne?

  • Add media

  • Has a working at height permit been completed?

  • Add media

  • Is there a rescue plan in place?

  • Add media

  • Have operatives completed working safely at height training?

  • Add media

  • Is scaffold provided as a safe working platform and means of access?

  • Add media

  • Is scaffold of appropriate duty rating?

  • Add media

  • Is scaffold constructed in accordance with AS1576?

  • Add media

  • Has scaffold been inspected in last 30 days and tagged?

  • Add media

  • Are tags displayed at all entrances to scaffold?

  • Add media

  • Has emergency access been considered in the design of scaffold?

  • Add media

  • Where work is being conducted from EWPs, are all machines in serviceable condition?

  • Add media

  • Are log books completed daily?

  • Add media

  • Have all penetrations or services in operational area of EWP been clearly identified and/or barricaded?

  • Add media

  • Are operators trained and hold appropriate licences if applicable?

  • Add media

Corrective Actions

    Corrective Actions
  • Description

  • Add media

  • Risk Rating

  • Action by

  • Date completed

  • Completed sign off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.