Title Page
-
Conducted on
-
Prepared by
-
Document No. QF/quality/PQA/23 Rev.01
-
Shift
10A: Application of Grease on Front & Back vertical Axles Sealant Ring
-
Equipment at the station: (A) Straightness checking gauge(B)Grease and Brush ,There is No other equipment at the work station.
-
Operator must wear apron and safety shoes.
-
DMI (Detail of Manufacturing Instruction must be displayed and operator must follow DMI
-
Positive control sheet must be displayed and operator must check positive control sheet check point and sheet must be fill by operator
-
Operator must follow check do check process
-
work station must be free from dust and unused material and tools.
-
Straightness checking gauge must be calibrated.
-
Grease must be free from dust contamination.
-
Red bin must be available for rejection material.
-
Waste part should not spread over shop floor and working table.
-
All material must be identify and placed at define location.
-
Operator must Skilled
-
Operator ID
20A: Assembly diaphragm 1.2 and diaphragm moulded shield with diaphragm shield driving Equipment
-
Equipment at the station: (A) Ultrasonic welding machine ,There is No other equipment at the work station.
-
Operator must wear Apron, Earplug & Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Positive control sheet must be displayed and check sheet must be fill by operator.
-
TPM Sheet must be fill by operator and maintenance team.
-
All pressure Gauge Indicator must be calibrated.
-
Work station must be free from dust, unused material and tools.
-
Operator must follow the check do check process.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Emergency switch must be in working condition.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled
-
Operator ID
10:Assembly of central mandrel, lever shield & vertical axle sub assembly with measuring unit housing
-
Equipment at the station: A)HMI machine b) vertical axle assembly SPM ,c) Air Gun
-
Operator must wear Apron and Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Work station light must be switched on and working.
-
Operator must follow the check do check process.
-
Positive Control Sheet must be available and fill by operator
-
TPM sheet must be fill by operator and maintenance Team
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Number of assemblies being processed by this stage should be one
-
Operator must Skilled
-
Operator ID
20:Diaphragm Assembly on MU housing ST 1
-
Equipment at the station: (A) Grease and Brush ,There is No other equipment at the work station.
-
Operator must wear Apron & Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Positive control sheet must be displayed and check sheet must be fill by operator.
-
Operator must follow the check do check process.
-
Grease must be free from dust contamination.
-
Conveyor must be fixed and stable.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled
-
Operator ID
30:Diaphragm Assembly on MU housing ST 2
-
Equipment at the station: (A)Grease and Brush ,There is No other equipment at the work station.
-
Operator must wear Apron & Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Positive control sheet must be displayed and check sheet must be fill by operator.
-
Operator must follow the check do check process.
-
Grease must be free from dust contamination.
-
Conveyor must be fixed and stable.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled
40:Assemble front & back covers with measuring unit housing sub-assembly.
-
Equipment at the station: (A) Front & Back cover assembly SPM (B) Air Gun(C) Thickness checking Gauge, There is No other equipment at the work station.
-
Operator must wear Apron & Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Positive control sheet must be displayed and check sheet must be fill by operator.
-
Pre control sheet must be fill by operator.
-
Thickness Gauge Must be calibrated.
-
Operator must follow the check do check process.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Emergency switch & Safety Curtain must be in working condition.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled
-
Operator ID
50A & 50: Applying adhesive sealant (Sikaflex221) & Fitment of Valve base and outlet with housing assembly
-
Equipment at the station: (A) HMI Machine (B) Air Gun(C) Weighing Machine, There is No other equipment at the work station.
-
Operator must wear Apron & Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Positive control sheet must be displayed and check sheet must be fill by operator.
-
Pre control sheet must be fill by operator.
-
Operator must follow the check do check process.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Emergency switch must be in working condition.
-
Red bin must be available for rejection material at stage.
-
Weighing Machine must be calibrated.
-
Sika Self life must not be expired.
-
Operator must Skilled.
-
Operator ID
60:Adhesive Sealant Curing
-
Equipment at the station: (A) HMI Machine (B) Barcode, There is No other equipment at the work station.
-
DMI (Detailed Manufacturing Instruction) must be displayed.
-
Work station must be free from dust, unused material and tools.
-
Work station light must be switched on and working.
-
Operator must maintain FIFO manner.
-
All equipment must be identify and placed at defined location.
-
Emergency switch and Safety Curtain must be in working condition.
-
Waste parts should not be spread over in the shop floor & working table.
-
Operator must Skilled.
-
Operator ID
70A:transmission gear and holder gear assembly
-
Operator must wear Apron and Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Operator must follow the check do check process.
-
MU Assembly part must be free from fleshes, burr, damage and moulding defect.
-
Angle Gear and transmission Gear must be rotate smoothly
-
All part must be properly locked.
-
Angle Gear must not be rotate in antilock wise
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
70:Tightness testing
-
Equipment at the station: (A) Tightness testing Jig (B) test to fail pass sample
-
Operator must wear Apron and Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Positive control sheet must be displayed and check sheet must be fill by operator.
-
All pressure Gauge Indicator must be calibrated.
-
TPM Sheet must be fill by operator and maintenance team.
-
Work station must be free from dust, unused material and tools.
-
Operator must follow the check do check process.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Number of assemblies being processed by this stage should be one
-
Emergency switch must be in working condition.
-
Operator must Skilled.
-
Operator ID
80:Oscillator lever Assembly
-
Equipment at the station :(A)Oscillatory Lever assembly Fixture (B)Grease
-
Operator must wear Apron & Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Grease must be free from dust contamination.
-
Positive control sheet must be available and must be fill by operator.
-
TPM sheet must be available and must be fill by operator and maintenance team.
-
Fixture must be fixed and stable while working and must be easy to operate.
-
Pressure Gauge Indicator must be calibrated.
-
Work station must be free from dust, unused material and tools.
-
Work station light must be switched on and working.
-
Operator must follow the check do check process.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must follow single piece flow process.
-
Operator must Skilled.
-
Operator ID
90A,90B:Assembly of SOV & SOV Functional Testing
-
Equipment at the station: (A) SOV functional testing Jig (B) Computer & Bar code Reader, There is No other equipment at the work station.
-
Operator must wear apron and safety shoes.
-
DMI (Detail of Manufacturing Instruction must be displayed and operator must follow DMI
-
Positive control sheet must be displayed and operator must check positive control sheet check point and sheet must be fill by operator
-
Operator must follow check do check process
-
work station must be free from dust and unused material and tools.
-
SOV functional test fixture must not be worn out.
-
Red bin must be available for rejection material.
-
Waste part should not spread over shop floor and working table.
-
All material must be identify and placed at define location.
-
Operator must Skilled
-
Operator ID
90:SOV assembly with measuring unit
-
Equipment at the station: (A) SOV -MU assembly fixture(B)Grease and Brush ,There is No other equipment at the work station.
-
Operator must wear apron and safety shoes.
-
DMI (Detail of Manufacturing Instruction must be displayed and operator must follow DMI
-
Positive control sheet must be displayed and operator must check positive control sheet check point and sheet must be fill by operator
-
Operator must follow check do check process
-
work station must be free from dust and unused material and tools.
-
SOV functional test fixture must not be worn out.
-
Red bin must be available for rejection material.
-
Waste part should not spread over shop floor and working table.
-
All material must be identify and placed at define location.
-
Operator must Skilled
-
Operator ID
100:Pressure Drop
-
Equipment at the station :( A) Pressure drop testing machine (B) Cir clip pliers
-
Operator must wear Apron & Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Grease must be free from dust contamination.
-
Positive control sheet must be available and must be fill by operator.
-
TPM sheet must be available and must be fill by operator and maintenance team.
-
Fixture must be fixed and stable while working and must be easy to operate.
-
Pressure Gauge Indicator must be calibrated.
-
Work station must be free from dust, unused material and tools.
-
Work station light must be switched on and working.
-
Operator must follow the check do check process.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
MU pressure transmitter must be calibrated.
-
Operator must follow single piece flow process.
-
Operator must Skilled.
-
Operator ID
110,120: Error Testing & Frame Assembly
-
Equipment at the station :(A)Error Testing Machine
-
Operator must wear Apron and Cap.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Work station light must be switched on and working.
-
Operator must follow the check do check process.
-
Positive control sheet must be displayed and operator must fill positive control sheet.
-
TPM sheet must be fill by operator & Maintenance Team.
-
All temperature, humidity & and pressure indicator must be calibrated
-
Temp. And humidity must be maintained as per testing Requirement.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
130A: Assembly of External Magnet
-
Equipment at the station: (A) External Magnate Assembly Fixture (B)Plug Gauge ,There is No other equipment at the work station.
-
Operator must wear apron and safety shoes.
-
DMI (Detail of Manufacturing Instruction must be displayed and operator must follow DMI
-
Positive control sheet must be displayed and operator must check positive control sheet check point and sheet must be fill by operator
-
Operator must follow check do check process
-
work station must be free from dust and unused material and tools.
-
Plug gauge must be calibrated
-
Go-no-Go recording Sheet must fill by operator
-
Red bin must be available for rejection material.
-
Waste part should not spread over shop floor and working table.
-
Safety curtain must be in working condition.
-
All material must be identify and placed at define location.
-
Operator must Skilled.
-
Operator ID
130B:Apply grease on Magnet Assembly and assemble with upper case
-
Equipment at the station: (A)Wrong arrow sample (B)Upper Case Holding Fixture(C) Weighing Machine ,There is No other equipment at the work station.
-
Operator must wear apron, gloves & Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Positive and precontrol sheet must be fill by operator.
-
TPM sheet must be fill by operator and maintenance team.
-
Operator must follow Check Do Check Process.
-
Grease weight log sheet must be fill by operator.
-
Grease dispensing nozzle must be dust free and nozzle’s all holes must be work.
-
Date of next calibration of Weighing machine and all pressure Gauge must be marked.
-
Weighing machine Alignment in analytical balance must be proper and machine must be stable.
-
Upper case assy. Fixture must be fixed and stable while working.
-
Work station must be free from dust, unused material and tools.
-
All material must be identify and placed at defined location
-
Emergency switch must be in working and stable condition.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
130:Mu with Upper case Sub assembly
-
Equipment at the station: (A) Barcode Reader (B)Upper Case Holding Fixture ,There is No other equipment at the work station.
-
Operator must wear apron & Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed with Latest revision no. and operator must follow DMI.
-
Work Station light must be switched on and working.
-
Work station must be free from dust, unused material and tools.
-
Upper case & barcode holding Fixture must be fixed and stable while working.
-
All material must be identify and placed at defined location.
-
Operator must follow single piece flow process.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
140A:Lower case Assembly
-
Equipment at the station: (A) cloths
-
Operator must wear apron, gloves& Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed with Latest revision no and operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
Emergency switch must be in working and stable condition.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled
-
Operator ID
140:Sika Flex dispensing on lower case
-
Equipment at the station: (A) HMI Machine (B) Sika Dispensing fixture (C)e) Weighing machine
-
Operator must wear apron, gloves, goggle & Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed with Latest revision no. and Operator must follow DMI.
-
Positive control sheet must be fill by operator.
-
precontrol sheet Must be fill by operator.
-
Weighing machine and pressure Gauge must be calibrated and Date of next calibration must be marked.
-
Weighing machine Alignment in analytical balance must be proper and machine must be stable.
-
Sika shelf life must be within expired date.
-
Work station must be free from dust, unused material and tools.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Emergency switch must be in working and stable condition.
-
Red bin must be available for rejection material at stage.
-
Preventive Maintenance sheet must be available and must be fill by operator and maintenance team.
-
Operator must Skilled
150: Initial Pressing of Band
-
Equipment at the station: (A) HMI Machine
-
Operator must wear apron, gloves, goggle & Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed with Latest revision no. and Operator must follow DMI.
-
Positive control sheet must be fill by operator.
-
Work station must be free from dust, unused material and tools.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Emergency switch & safety curtain must be in working and stable condition.
-
Red bin must be available for rejection material at stage.
-
Preventive Maintenance sheet must be available and must be fill by operator and maintenance team.
-
Operator must Skilled
-
Operator ID
160: Final Band roller pressing
-
Equipment at the station: (A) HMI Machine (B) SCISSORS(C) CLOTHS
-
Operator must wear apron, gloves, goggle & Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed with Latest revision no. and Operator must follow DMI.
-
Positive control sheet must be fill by operator.
-
Work station must be free from dust, unused material and tools.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Emergency switch & safety curtain must be in working and stable condition.
-
Red bin must be available for rejection material at stage.
-
Preventive Maintenance sheet must be available and must be fill by operator and maintenance team.
-
Operator must Skilled
170: Adhesive Sealant Curing
-
Equipment at the station: (A) HMI Machine (B)BAR CODE READER
-
Operator must wear apron, gloves, goggle & Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed with Latest revision no. and Operator must follow DMI.
-
Work station must be free from dust, unused material and tools.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Emergency switch & safety curtain must be in working and stable condition.
-
Temperature and humidifier sensor must be calibrated and next calibration date must be marked.
-
Operator must Skilled
-
Operator ID
180: Leakage Testing of Gas Meter
-
Equipment at the station: (A) HMI Machine (B)BAR CODE READER(C)BRUSH
-
Operator must wear apron, safety shoes & earplugs.
-
DMI (Detailed Manufacturing Instruction) must be displayed and operator must follow DMI
-
Positive Control Sheet must be displayed at the workstation. and must be fill by operator
-
TPM sheet must fill by operator and maintenance Team in defined interval.
-
Work station must be free from dust, unused material and tools.
-
Meter fixture in LTM must not be worn out.
-
Operator must follow the check do check process.
-
Water must be clean in water tank and must be filled at defined level in the tank.
-
Date of next calibration of “Pressure Gauges” must be marked.
-
Emergency Switch of machine must be work.
-
All materials and tools must be identify and placed at defined location
-
Waste parts should not be spread over in the shop floor & working table. 3
-
Operator must Skilled
-
Operator ID
190,200: Assembly of Internal Magnet + EU on Gas meter, Functional testing
-
Equipment at the station: (A) TORQUE WRENCH (B)SCREW DRIVER(C)WRIST BELT
-
Operator must wear anti static apron, Safety Shoes and wrist belt.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Positive Control sheet must be displayed at the workstation and must be fill by operator
-
Precontrol sheet must be displayed at the workstation and must be fill by operator
-
Operator Must followed Check Do Check Process.
-
Wrist belt must be test by operator at the starting of line.
-
Work station must be free from dust, unused material and tools.
-
Date of next calibration of screw driver must be marked.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
All electrical connection should not be lose and should be safe.
-
Red bin must be available for rejection material at stage.
-
Operator must followed single piece flow process.
-
Operator must Skilled
-
Operator ID
190A: Assembly of Internal magnet
-
Equipment at the station: (A) Go-No-Gauge (B)Screw Driver
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Positive Control sheet must be displayed at the workstation and must be fill by operator
-
Operator Must followed Check Do Check Process.
-
Work station must be free from dust, unused material and tools.
-
Date of next calibration of screw driver & gauge must be marked.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
210:MID seal assembly
-
Equipment at the station: (A) MID seal pressing Machine
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Operator Must followed Check Do Check Process.
-
Work station must be free from dust, unused material and tools.
-
Safety curtain must be in working condition.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
220:Brass Nut Tightening
-
Equipment at the station: (A) Brass nut tightening fixture (B) Screw Driver
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Operator Must followed Check Do Check Process.
-
Work station must be free from dust, unused material and tools.
-
Safety curtain must be in working condition.
-
All material must be identify and placed at defined location.
-
Positive control sheet must be fill up by operator.
-
Pre control sheet must be fill up by operator.
-
Screw Driver must be calibrated.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
230:Plastic seal assembly
-
Equipment at the station: (A) Plastic Seal pressing Machine ,There is No other equipment at the work station.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Operator Must followed Check Do Check Process.
-
Work station must be free from dust, unused material and tools.
-
Safety curtain must be in working condition.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled.
-
Operator ID
240,250,260:G-mat,Laser Printing, Customization
-
Equipment at the station: 1. Test Bench, 2.Laser Printer, There is No other equipment at the work station.
-
Operator must wear apron, Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Positive Control sheet must be displayed at the workstation and sheet must be fill by operator
-
All electrical connection must not be loose and must be safe.
-
Work station must be free from dust, unused material and tools.
-
Date of next calibration of sonic nozzle, temp., and pressure and humidity sensor must be marked.
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over the shop floor & working table.
-
Printing quality must not be spread and must be readable.
-
Fume extractor must be in working condition.
-
Customization Batch must be as per Sales order.
-
Preventive maintenance should be done by maintenance team and operator.
-
Operator must follow single piece flow process
-
Operator must Skilled
-
Operator ID
270,280,290:KIOSK,Asset File Generation, Final Locking of Subassembly of port cover
-
Equipment at the station:(A) holding fixture,(B) Label dispenser(C)Barcode reader(D)Barcode Printer There is no other equipment at the workstation
-
Operator must wear Apron, Safety Shoes.
-
DMI must be displayed on station, Operator must follow DMI.
-
Operator Must followed Check Do Check Process.
-
Meter holding fixture must be stable and fix while working.
-
Work station must be free from dust, unused material and tools.
-
All material must be identify and placed at defined location.
-
All electrical connection should not be loose and should be safe.
-
Red bin must be available for rejection material at stage.
-
Operator must Skilled
-
Operator ID
310:Inspection Stage
-
Operator must wear apron & Safety Shoes.
-
Work Instruction Must be displayed and Inspector must followed work instruction.
-
Inspection Sheet Must be available
-
Work Station light must be switched on and working.
-
Work station must be free from dust, unused material and tools.
-
Red bin must be available for rejection material at stage.
-
Operator must be followed single piece flow process.
-
Operator must Skilled
-
Operator ID
320,340,350:Primary packing and stretch with wrapping
-
Equipment at the station: (A) Bar code reader (B) Wrapping machine, There is No other equipment at the work station.
-
Operator must wear Apron, Gloves & Safety Shoes.
-
DMI (Detailed Manufacturing Instruction) must be displayed and Operator must follow DMI.
-
Fixtures must not be worn out.
-
UN approval certificate stamp and hazardous label must be print on CFB box.
-
Work station must be free from dust, unused material and tools
-
All material must be identify and placed at defined location.
-
Waste parts should not be spread over in the shop floor & working table.
-
Operator must be followed single piece flow process.
-
Operator must Skilled
-
Operator ID
-
Line Supervisor
-
Auditor