ensuite

  • floor tiles in shower area laid before walls

  • floor tiles in shower areas lower than water bar

  • wet area niches have fall and no chipped tiles

  • all electrical wiring pulled

  • additional tiles required for areas closer that 70mm to sink

  • correct tiles installed

  • sufficient gaping between water bar and tile in shower areas no grout fill

  • expansion tiled areas clear of grout

  • all external angles box trim straight and true and butt joins aligned

  • vertical water bar in place

  • No lipping and misalignment of tiles

  • hole cutouts in penetrations not oversized

  • correct height of shower rail as per plan

  • toilet inlet correct for Btw or bottom inlet . Hole not too big .

  • 30mm overhang allowance for shower screen in place

  • tiling clear of foreign surfaces i;e benchtops

  • Grout color Consistent and uniform in color

main Bathroom

  • Grout color Consistent and uniform in color

  • tiling clear of foreign surfaces i;e benchtops

  • hole cutouts in penetrations not oversized

  • No lipping and misalignment of tiles

  • vertical water bar in place

  • all external angles box trim straight and true and butt joins aligned

  • expansion tiled areas clear of grout

  • sufficient gaping between water bar and tile in shower areas no grout fill

  • correct tiles installed

  • additional tiles required for areas closer that 70mm to sink

  • all electrical wiring pulled

  • wet area niches have fall and no chipped tiles

  • floor tiles in shower areas lower than water bar

  • floor tiles in shower area laid before walls correct fall , watste not raised

  • bathtub free from Marks .

  • bath Hob correct fall

  • bath hob tiles not touching bathtub and internal cuts clear of bathtub

  • bath hob tiles align with the floor tiles when possible (if not advise the owner )

  • toilet inlet correct for Btw or bottom inlet . Hole not too big .

  • correct height of shower rails as per plan

  • 30mm overhang allowance for shower screen in place

Powder room

  • correct pattern to splash back

  • toilet inlet correct for Btw or bottom inlet . Hole not too big .

  • additional tiles required for areas closer that 70mm to sink

  • all electrical wiring pulled

  • correct grout and consistency with no colour variances

  • correct tiles installed

  • sufficient gaping between water bar and tile in shower areas no grout fill

  • Vanity secured

ensuite 2

  • floor tiles in shower area laid before walls correct fall , waste not raised

  • floor tiles in shower areas lower than water bar

  • wet area niches have fall and no chipped tiles

  • all electrical wiring pulled

  • additional tiles required for areas closer that 70mm to sink

  • correct tiles installed

  • sufficient gaping between water bar and tile in shower areas no grout fill

  • expansion tiled areas clear of grout

  • all external angles box trim straight and true and butt joins aligned

  • vertical water bar in place

  • No lipping and misalignment of tiles

  • hole cutouts in penetrations not oversized

  • correct height of shower rail as per plan

  • toilet inlet correct for Btw or bottom inlet . Hole not too big .

  • 30mm overhang allowance for shower screen in place

  • tiling clear of foreign surfaces i;e benchtops

  • Grout color Consistent and uniform in color

entry

  • correct tile pattern

  • tiles clear from walls to allow for caulk

  • correct tiles laid

  • no lippage greater that 2mm ( discuss with Manufacturer if tiles are bowed

  • correct grout and consistency with no colour variances

  • flashing for front door covered .

  • correct step at garage ingress door ( 190 max )

  • expansion for tiling every 6 meters . Grout left clear

Kitchen

  • correct tile

  • correct pattern

  • wiring pulled through

  • splashback tile straight due to horizontal light of rangehood

  • floor tiles clear from Joinery to allow for Caulk

  • rangehood tiles supported to allow for a canopy rangehood

  • scratches on benchtops due to tiler not covering them

  • tiled splashback to sides of sink if sink is closer than 70mm

  • correct grout and consistency with no colour variances

  • proximity of hot plate to tile splashback correct as per manufacturers warranty

  • window surround tiled box trim secured

butlers pantry

  • correct tile

  • correct pattern

  • wiring pulled through

  • splashback tile straight due to horizontal light of rangehood

  • floor tiles clear from Joinery to allow for Caulk

  • rangehood tiles supported to allow for a canopy rangehood

  • scratches on benchtops due to tiler not covering them

  • tiled splashback to sides of sink if sink is closer than 70mm

  • correct grout and consistency with no colour variances

  • proximity of hot plate to tile splashback correct as per manufacturers warranty

  • window surround tiled box trim secured

family room

  • correct tile pattern

  • correct tiles

  • expansion... grout clear every 6m for caulk

  • correct grout and consistency with no colour variances

  • tiles clear from walls to allow for caulk

  • no lippage greater than 2mm ( if so has the supplier been informed for bowed tiles )

Laundry

  • waterbar in place and clear of grout for silicone

  • splashback as per plans and on side of trough if closer than 70mm

  • tiles no lippage

  • tiles not touching cabinetry doors and walls and clear for caulk

  • correct tiles

  • correct hole cut out size around wall mixers

  • floor waste has fall and waste not raised higher than tiles

  • Metal laundry cabinet in and square . Floor of cabinet tiles laid

  • correct tile pattern

  • correct grout and consistency with no colour variances

  • wiring pulled through

Exterior tiles

  • correct fall to tiles (not holding water )

  • Tiles not touching perimeter walls

  • Tile overhang on slabs to allow for edge tile .No excessive overhangs

  • no excessive moisture in grout and uniform color

House Keeping

  • Bin in place and being used by trades

  • tile wash up not over brick walls or washed down waste pipes

  • Tiles left neatly on site . overabundance returned to company

  • Site left in a safe manner and house locked up

  • G.J sign and danger sign and Hazard co sign up.

  • Job left clean, rubbish in bin.

Are any rectification works required?

  • Works required

  • Date to be completed

  • Signature of person conducting the Audit

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.