Title Page
-
I.D.I. Job Number
-
Job Site Name
-
Conducted on
-
I.D.I. QAQC Inspector
-
Job Site Area of QAQC Inspection
-
Confirm for updated drawings, plans & specs
-
Have all shop drawings and truss drawings been approved?
-
Are we using a spreader bar to install trusses?
-
Are all trusses free of damage from shipping?
-
Are we installing the correct number of fasteners into the truss?
-
Are we installing the correct number of fasteners into the bearing point?
-
Have you verified that the fasteners have not been over tightened or stripped?
-
Are all fasteners installed in the correct holes of the clips?
-
Has all X bracing been installed correctly with a maximum of 20’ in-between the braces?
-
Has all bracing been installed 100% at the end of the day?
-
Has lateral load bracing been installed?
-
Are the trusses plumb and level after the bracing has been installed?
-
Have the jack trusses been installed to the girder truss correctly?
-
Has all bracing been checked before the installation of the sheathing?
-
Confirm clean-up of our material and scrap?
-
Did you walk the job site with the GC?
-
Comments
-
Sign Off
-
I.D.I. QAQC Inspector