Information

  • Contractor Name

  • Prepared by

Audit Scope

  • Audit Type (multiple selection)

  • Audit Scope

Company Procedures

Management Systems

  • Q1. Is the company aware of the Certass logo use policy, technical handbooks, scheme rules (available from the Certass members area)

  • Q2. What are the management procedures for the company? (tick all that apply)

  • PAS2030 Management System

  • ISO9001/14001 Management System

  • Other Externally audited management system

  • Informal internal management procedures

  • Q3. If Applicable - Does the system meet all Green Deal PAS2030 requirements, including site related processes and paperwork

  • Outline details of the management systems

  • Q4. Are the Management systems adequate to operate the business?

  • Observations / Comments

Complaints Handling

  • Q5. Was a complaints handling procedure available?

  • Q6. Are any complaint records available to review?

  • Q7. Does the contractor have an adequate method for recording and tracking consumer complaints?

  • Observations / Comments

Health and Safety Procedures

  • Number of Employees

  • Q8. COSHH assessments and other relevant risk assessments inspected

  • Q9. Accident Book Inspected

  • Q10. First Aid person appointed?

  • Observations / Comments

Office Based Staff Assessment

  • Company Principals are suitably qualified and experienced.

  • Q12. Suitably qualified and experienced administrative staff are employed, appropriate to the nature of the work.

  • Q13. Site supervisor’s work is adequately allocated and monitored by Company Principals.

  • Q14. The level of site supervision is adequate and appropriate to the nature of the work.

  • Q15. Site supervisory staff are suitably qualified and experienced.

  • Q16. Do company principles and supervisors understand the Building Regulation issues relating to the installation which must not make the situation worse

  • Q17. Do company principles and supervisors understand the mandatory requirements of the Building Regulations for the installation

  • Q18. Is the contractor aware of what they can and can’t register with Certass e.g cant register porches, conservatories, new extensions

  • Observations / Comments

Sub-Contractor Allocation

  • Q19. Does the company use sub- contractors

  • Q20. Contractor has appropriate mechanisms for ensuring that sub-contractors remain aware of changes to standards and regulations.

  • Q21. Contractor has appropriate mechanisms for choosing sub-contractors, to ensure that they are suitably qualified and experienced.

  • Q22. Contractor has appropriate mechanisms for ensuring that the quality of sub-contractors work will ensure that the finished works are fit for purpose.

  • Observations / Comments

Job contract review, sample 3 job files

  • List job files sampled

  • Q23. Does the company paperwork issued to consumers have the company details displayed

  • Q24. Contract/quotation is written in clear unambiguous English

  • Q25. Reference is made in the contract to cooling off periods or an opt out clause is completed by the consumer

  • Q26. Scope of work is simply presented and adequately described.

  • Q27. Timetable for the works stated.

  • Q28. Payment rules are clearly stated.

  • Q29. Associated documents are available e.g survey notes, consumer queries

  • Q30. Evidence that purchased products are compliant to thermal performance requirements

  • Materials used are covered by appropriate and relevant quality assurance provisions. e.g CE Marking

  • Observations/comments

Site Operatives

Fitting Teams

  • Number of Fitting Teams

  • Enter Qualified Fitting Team member

  • Person
  • First Name

  • Last Name

  • Date of Birth

  • Qualification

  • Q32. Are installers all suitably qualified or in suitable training programmes?

  • Observations/Comments

Surveyors

  • Number of surveyors

  • Surveyor Details

  • Person
  • First Name

  • Surname

  • Date of Birth

  • Qualification

  • Q33. Are all surveyors suitably qualified or in suitable training programmes?

  • Observations/Comments

Sub-contractors

  • Do subcontract installers have suitable qualifications

  • Observations/Comments

Site Installation audit

Site details

  • Installation Address
  • Property Description

  • Front Elevation photo

  • Installation details /scope of works

  • Q35. BUILDING REGULATION CHECKS (CLICK TO THE RIGHT TO ADD EACH INSTALLATION LOCATION)

  • INSTALLATION CHECKS
  • Location

  • Structural Stability

  • Fire Safety

  • Resistance to contaminants and moisture

  • Toxic Substances

  • Resistance to sound

  • Ventilation

  • Sanitation, Hot Water Safety and Water Efficiency

  • Drainage and waste disposal

  • Heat producing appliances

  • Protection from falling

  • Conservation of fuel and power

  • Access to and Use of Buildings

  • Glazing safety

  • Electrical Safety

  • Approved Document 7 (Workmanship and Materials)

  • Scheme Rules

Quality and Customer Care

  • Q36. Quality Index (1 worst, 5 Average, 10 Best - prize winning standard)

  • Q37. Does the installation meets the specification and survey note requirements

  • Q38. Has the consumer been provided with a contract, guarantee and aware of an IBG

  • Any feedback from the consumer

EWI

  • Q39. Is the installation for External Wall Insulation

  • N/ A in checklist = Not Applicable or Not Able to view at stage of contruction

General

  • Correct materials on site?

  • Correct storage of materials?

  • Base track level?

  • Cills correctly fitted?

Insulation Boarding

  • Bossed render removed & dubbed out?

  • Verge trims fitted correctly?

  • Board sizes greater than 200mm?

  • Base track level?

  • Boards bedded if required?

  • Fixing pattern correct?

  • L shapes around windows?

  • Gaps between boards filled?

  • Solidly fixed?

  • Sealing tape at abutments / openings / base / verge?

  • Boarding flat?

  • Firebreaks in place and stainless pins used?

  • Insulation rasped / joints smoothed off?

Base Coat Render

  • Beading lined and levelled?

  • Base coat notch trowelled?

  • Stress patches in place?

  • Mesh fully embedded if applicable?

  • Correct depth of base coat?

  • Flattened off sponge smooth finish?

Finish

  • Printing correct colour, no runs?

  • Texture /Pebble dash / Brickslip properly applied, even finish?

  • Rubbed up to proper thickness, no bald spots?

Special details

  • Movement/ Expansion joints correctly fitted, fixed?

  • Overpainted? Even, smooth finish?

  • Ashlar details? Sufficient drip, smooth finish?

Observations

  • Observations / comments

Non Conformance Issues

Non Conformances

  • Q40. Are there any non conformance issues

  • N/C List

  • Issues
  • Location

  • N/C Description

  • Requirement for improvement

Sign Off

Certification Recommendation

  • Recommendation for Certification

  • Justification for recommendation

  • Action plan agreed for any remedial action

  • Contractor signature

  • Auditor Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.