AUDIT PREPARATION
-
Confirm field staff will be working on site during the audit visit
-
Do audit personnel have appropriate PPE for the field visit?
-
Do audit personnel have permission to access the proposed audit site?
ARRIVAL AT SITE
-
Survey task being undertaken?
-
Initial impression of job site
-
Applicable site images to support the inspection
SITE REVIEW
-
Have all company vehicles been parked in a safe manner and location?
-
Corrective action implemented during visit
-
Should vehicle beacon be operational whilst on site?
-
Are personnel wearing the appropriate PPE for the job site?
-
Corrective action implemented during visit
-
Has the JSA been completed and signed off?
-
Corrective action implemented during visit
-
Is all survey equipment clear of footpaths and roadways?
-
Corrective action implemented during visit
-
Should a Traffic Management Plan (TMP) be used to improve on road safety?
-
All on road works shall cease until appropriate TMP and signage can be coordinated for site.
-
Do personnel have a work instruction from the project manager?
SITE DISCUSSION
-
Do personnel have any concerns not identified or observed during the audit?
-
Notes for personnel discussion
COMPLETION OF VISIT
-
Has all non-conformance been rectified during the audit visit?
-
Actions taken on site
-
Can the works continue safely?