Title Page
Post-tensioning ITP Cut & Seal
-
Client
-
Post-tensioning Cut & Seal ITP prepared by
-
Project Name
-
Project Number
-
Level and pour number
-
Date of Cut & Seal
-
Location
-
This Post-tensioning Inspection & Test Plan (ITP) must be completed for each post-tensioned slab cut & sealed on the project.
Extension Approval
-
Has the Engineer/Main Contractor approved the stressing extensions?
- If Yes, Type the name of approver, date and time
- If No, DO NOT proceed
Preparation to Grout
-
Have the strands been cut to provide sufficient cover?
-
Have the external blocks been coated?
-
Have the pockets been sealed with a dry pack mix? (Dry Mix + 4 Bags of Sand & Cement + 1 Bag of Cement)
Tendons ready for grouting
-
Does a clear passage of air pass through all Tendons from one end to the other?
-
Note Tendon numbers that required unblocking/drilling.
-
Note Tendon numbers that required intermediate grouting points added.
-
SRG Leading Hand - I confirm that all post-tensioning tendons to the above noted slab have been cut and sealed.
-
Main Contractor