Title Page

  • Module 2 mains jointing

  • ENWL training academy

  • Conducted on

  • John lee

  • Personnel

Service to service jointing

Mains jointing

  • Waveform bottle end

  • Waveform bottle end

  • Waveform to Waveform live cut and straight joint (test joint)

  • Waveform to Waveform live cut and straight joint live both ways

  • Waveform to waveform live cut and straight joint including service

  • Waveform to waveform breech joint

  • Waveform to waveform breech joint (test joint)

  • Pole top termination on 3c waveform

  • Pole top termination on 4c waveform

  • Terminate 3c waveform in Resin Linkbox

  • Terminate 3c waveform in Resin Linkbox (test joint)

  • Terminate waveform cable in MOD unit

  • Terminate waveform cable in MOD unit (test joint)

Service to mains jointing

Mains jointing

  • 3c waveform breech off 4c PILC main

  • 4c waveform (old colours) breech off 4c PILC main (test joint)

  • 4c PILC live cut and straight joint to 3c waveform

  • 4c PILC live cut and straight joint to 4c waveform (live both ways) old colours (test joint)

  • 3c Waveform breech joint off Consac main

  • 3c Waveform breech joint off Consac main

  • Consac live cut and straight joint to 3c waveform (test joint)

  • Consac live cut and straight joint to 3c waveform

Service position tests

Polarity and ELI testing

  • CNE cut-out correct polarity found?

  • CNE cut-out no neutral found?

  • CNE cut-out cross polarity found?

  • CNE cut-out dead found?

  • SNE cut-out correct polarity found?

  • SNE cut-out cross polarity found?

  • SNE cut-out No neutral found?

  • SNE cut-out DEAD found?

  • Correct ELI reading for CNE cut-out identified (max reading 0.35 Ohms)?

  • Correct ELI reading for SNE cut-out identified (max reading 0.80 Ohms)?

Fault finding on 4c waveform

Testing on 4c mains cable

  • Phase down found?

  • Healthy cable found?

  • No neutral found?

  • No earth found?

  • Phase and neutral cross found?

  • Cable dead found?

  • Phase to phase (weld) found?

Insulation resistance and continuity

Insulation resistance and continuity testing on 3c 25mm CNE

  • Did they find short between 2 phases?

  • Did they find the cable healthy?

  • Did they find broken phase?

Insulation resistance and continuity testing 3 x single phase 35mm CNE cables

  • Were the 2 healthy cables found?

  • Was the cable with the dead short found?

Signatures

  • Summary

Signatures

  • Trainers signature

  • Trainees signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.