Information
-
Document No.
-
Audit Title
-
Client / Site
-
Name of Consulting Engineers.
-
Name of Principal Contractor.
-
Conducted on
-
Prepared by
-
Location
-
Personnel
OHS Administration
-
CR 3(1) Notification of Construction Work in file incl. proof.
-
CR 4(1)(g) Current Letter of good standing in file.
-
CR 4(1)(a) Client's OHS Spec in file.
-
CR 4(2) OHS Plan approved and on site.
-
S.7(1) Company OHS Policy signed by CEO.
-
OHS Policy communicated to employees?
-
GAR 4 Copy of the OHS Act and it's Regulations.
-
Latest organogram on site.
-
OHS Site Rules available on site.
-
Has OHS Site Rules been communicated to labour force?
-
Is there proof in the safety file?
OHS Legal Appointment
-
Are the following appointments in place on site?
-
Project Manager
-
Short CV to verify competence?
-
Construction Works Supervisor
-
Short CV to verify competence?
-
Assistant Construction Works Supervisor
-
Short CV to verify competence?
-
Construction Safety Officer.
-
Training certificate in place?
-
Risk Assessor
-
Training certificate in place.
-
Incident investigator
-
Training certificate in place.
-
First aider
-
Valid first aid training certificate in place.
-
Health and Safety Rep.
-
Training certificate in place.
-
Construction Mobile Plant Operators
-
Competency certificate in place.
-
Medical certificate of fitness in file.
-
Fire equipment inspector
-
Training certificate in place?
-
Hand tools inspector
-
Portable electrical tools inspector.
-
HCS Controller
-
Emergency Coordinator
-
Stacking & Storage Supervisor
Training
-
All employees inducted.
-
Induction attendance register completed?
-
Weekly toolbox talks conducted.
-
Toolbox talk attendance register completed?
Hazard Identification Risk Assessment
-
Overall risk assessment completed for project?
-
Safe work procedures in place for high risk activities?
-
Monitoring and reviewed plan in place?
-
Risk Assessment reviewed for current month?
-
HIRA and SWP communicated to employees?
Inspection Registers
-
PPE Issue Register
-
Hand tools register
-
Portable Electrical Tools register.
-
Daily mobile plant register.
-
Daily small plant register.
-
First aid contents register.
-
OHS Rep register
-
Facilities register
-
Fire extinguisher register.
-
Lifting tackle register.
Contractor Management
-
Mandatory agreement in place between client & principal contractor.
-
PC signed mandatory agreements with other contractors?
-
PC appointed each contractor.
-
Safety plans in place for each contractor.
-
Letter of good standing in place for contractors.
-
Each contractor appointed at least a Supervisor on site.
-
Monthly audit conducted on each subcontractor?
Public Safety
-
Campsite enclosed with fencing.
-
Safety symbolic signage in place.
-
All openings covered or fenced off?
-
General housekeeping on site.
Emergency Preparedness
-
Emergency numbers displayed in site office.
-
Emergency procedures displayed in site office.
-
Siren / hand held siren available on site.
-
Adequate amount of fire extinguishers on site.
Incident investigation
-
Incident investigation/ reporting procedure in place.
-
Blank copies on the Annexure 1 forms in file.
-
Blank copies of the WCA forms in file.
-
Number of section 24 incidents for current month.
First Aid Measures
-
Sufficient no. of first aid boxes on site.
-
First aid readily available.
-
First aid box fully stocked.
-
Name of first aider displayed in site office.
-
Signs posted up instructing workers to report all injuries to site office.
-
Number of first aid cases reported for current month.
Chemical Safety
-
MSDS available for:
-
Petrol
-
Diesel.
-
Cement
-
Others
-
MSDS's communicated to employees?
Traffic Accommodation
-
Traffic accommodation plan approved.
-
Flag men stationed correctly.
-
Flagging procedures adequate.
-
Flag men trained on site.
-
Traffic warning signs as per plan.
-
Amber flashing lights operational.
-
Cones and drums in place.
-
Delineators spaced correctly - no bricks used for support.
-
Danger signs in place.
-
New Jersey barriers in place as per plan.
-
High visibility clothing worn.
-
Amber flashing/ rotating lights fitted to construction vehicles?
-
Additional Non-compliances found on Site.
-
In order to PASS this audit, the contractor must achieve 90% compliance.
-
Achieved 90% and above: PASS
-
Achieved 89% and below: FAILED
-
I herewith my signature, declare that the above results of the audit done by me, is a true and correct reflection of the site's legal compliance, measured against the Occupational Health and Safety Act, Act no 85 of 1993.
-
Quantec Safety Consultancy Cell: 0785886415