Information
-
Document No.
-
Audit Title
-
Client / Site (displayed on first page)
-
Conducted on
-
Prepared by
More than one auditor?
-
Additional auditors
-
Signage and delineation at entrance to work area erected
-
Condition of internal roads maintained to acceptable standard
-
Windrows and barricading in place
-
Windrows constructed to correct height (half wheel height minimum)
-
No registrable plant is to be used on the project unless proof of registration is provided
-
All vehicles are fitted with flashing rotating amber beacons and they are operational
-
Audible reverse alarms are fitted and operational on all plant equipment
-
Earthmoving equipment using correct radio communication
-
Pre-Start inspection of the work area (and mobile plant) conducted
-
Current Permits / Certificates in place for the earthworks (Eg: ground penetration)
-
Is the disturbance boundary fence clearly marked and maintained (Eg: Salt Marsh area, no-go areas)?
-
Are internal road intersections clearly sign posted?
-
Are Traffic Management plans current?
-
Are contractor employees trained in / familiar with their Traffic Management Plan?
-
Are Safe Work Method Statements in place for earthmoving activities involving mobile plant?
-
Managers, Supervisors and employees are familiar with the requirements of the Construction Environmental Management Plan?
-
Noise mitigation and attenuation measures in place for plant and equipment to limit construction noise (EMP PDS 2)
-
Dust prevention is identified as a priority within pre-start meetings, JSEA's and task planning (EMP PDS 4)
-
Measures are in place for effective dust management and suppression (EMP PDS 4)
-
Dust is being monitored and data used to inform site management and suppression (EMP PDS 5)
-
Bunds are in place for mechanical equipment (fuel-powered) such as generators, pumps and fuel trailers. (EMP PDS 9)
-
Oil spill response kits stocked and located in appropriate areas and staff trained in their use (EMP PDS 10)
-
Employees/ Supervisors aware of process to be followed if a potential heritage or Aboriginal site identified (EMP PDS 11)
-
Stormwater/ groundwater Management Plan is being followed and measures in place to contain and manage discharges (EMP PDS 12)
-
Decommissioned landfill site delineated on site plans. No trenching of the pre-existing capping layer in this area (EMP PDS 14)
-
Procedures in place to manage bulk earthworks and acceptance and relocation of soil throughout site (PDS 14)
-
Inert waste streams are being segregated and appropriately managed (EMP PDS 14)
-
Odorous/stained soils have been stockpiled, labelled, bunded and appropriate testing and management has been in accordance with the Soil Management Plan. (EMP PDS 14)
Actions required?
-
Action?
-
-
Allocated to?
-
By date
-
Add location
-
Signed PoMC Representative:
-
Signed Principal Contractor Representative (optional):