Information
-
PCP EMP for Construction - PDS 12 Stormwater and Groundwater Management
-
Document No.
-
Audit Title
-
Client / Site (displayed on first page)
-
Conducted on
-
Prepared by
More than one auditor?
-
Additional auditors
-
Frequency: Everyday during dry conditions
-
Sed pond water level at or below 50% capacity?
-
ACTION: Determine contractor management requirements
-
Sed pond capacity can accommodate anticipated rain events (review weather conditions)?
-
ACTION: Determine contractor management requirements
-
Controls:
Silt logs
Diversion drains
Cut off drain
Gravel bags
Spillway -
Controls in place and working effectively?
-
ACTION: Determine contractor management requirements
-
Are controls clear of build-up?
-
ACTION: Ask contractor to clean
-
Are silt fences in place along site boundary around excavated areas/stockpiles?
-
ACTION: Ask contractor to rectify
-
Are silt fences appropriately anchored/secure?
-
ACTION: Ask contractor to rectify
-
Frequency: Weekly
-
Do water holding tanks have sufficient capacity?
-
ACTION: Determine contractor management requirements
-
Temporary piped drainage working effectively?
-
ACTION: Determine contractor management requirements
Rain event
-
Has there been a rain event?
-
If storm event, has the contractor checked controls within the first 2 hours
-
ACTION: Contractor to raise as incident and rectify
-
If prolonged rain, has contractor checked controls 3 times a day
-
ACTION: Contractor to raise as incident and rectify
-
Are public roads clear of dirt and mud?
-
ACTION: Ask contractor to clean
-
If storm water is leaving the site, is it controlled?
-
ACTION: Contractor to raise as incident and rectify
-
If pools of sediment laden water present outside site boundary, are sediment controls working?
-
ACTION: Ask contractor to rectify
-
Once sed pond spillway has been constructed; if there has there been overflow have contingency plans and water testing occurred?
-
ACTION: Overflow is the contingency plan and subject to water quality testing and recording (refer to dewatering monitoring requirements)
-
Has extreme rainfall that triggered a contingency response been reported as an incident?
-
ACTION: Ask contractor to rectify
-
Further observations
-
Add media
-
Signed PoMC representative:
-
Signed principal contractor representative (optional):