Title Page

  • Location

  • Type in your address below as backup at all times

  • Address

  • Take Photo of Front LetterBox including overview of house.

  • Conducted on

  • Prepared by

Pergola's are to be removed and replaced with a patio.

Validate Pergola Information

  • Where is Pergola located?

  • Confirm pergola type and size is as per spreadsheet

  • Scope of Work - Site measure. Upload site plan sketch

Variations

Electrical

  • LIGHTING DEFINITION: Only rear patio replacement to have lighting installed [adequate = 1 batten for small areas, 2 for larger areas.]

  • Is there lighting installed under patio structure? Take Photo of location of lighting. How many lights are installed?

  • Take photo of completed installation

  • Does conduit for carport lighting need to be isolated and reinstated?

Variations Other

  • Is there any roof top infrastructure that will interfere with the patio works?

  • What is the impediment?

  • If other describe details.

  • House Sheeting - Is there any sheeting requiring replacement?

  • Length of roof sheet/s to be replaced

  • Number of sheets required.

  • Any other items

Builders Ingoing Assessment

  • This page is for the builder to document whatever they require to assist with on the job management.

  • Take photos of external area and make notes as required

  • Take photos of eave lining area adjacent to the worksite prior to commencing

Builders Handover and ITP

Roof Strengthening - Batching

  • Builder must answer all questions and take clear photos showing outcome achieved.

  • Batch number

  • Take photo of eave connections looking down the trusses.

  • Take a photo of the horizonal strap bracing to trusses.

  • Take a photo of the HIP connections

  • Take a photo of any Gallows Bracket connections

  • Take a photo of the truncated & girder truss strengthening and other connections for Batch 4 properties

  • Take photos of RHS to wall plate and to hanging beam connections

  • Take an overview photo of the completed installation before closing roof

  • Take a photo of sisilation before resheeting

  • Take a photo of completed roof sheeting and flashing reinstatement.

Variations - take photos and add description

  • Variation 1

  • Variation 2

  • Variation 3

  • Variation 4

Patio Installation

  • Footing pre-pour [all columns]

  • Is mesh evident in concrete slab? If not provide details of larger footing size and tie-in to slab.

  • Finished hardstand

  • Patio connection details

  • Overall completion photo

Builder Completion

  • Take photos of external area to confirm no damage on completion.

  • Take photos of eave lining area adjacent to works to confirm no damage on completion

  • Record Date and Time of ITP inspection completed.

  • Full Name of Person Completing ITP Inspection

WEL Representitive Review

  • Is Practical completion achieved? Record Actions

  • Record date and time of review completed

  • Name of WEL Representive who has reviewed and completed.

  • PC certificate Issued and actions registered

  • Has Final Completion been achieved. All actions completed, evidence provided and uploaded to Property House Folder in Sharepoint.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.