Title Page
-
Location
-
Type in your address below as backup at all times
-
Address
-
Take Photo of Front LetterBox including overview of house.
-
Conducted on
-
Prepared by
Pergola's are to be removed and replaced with a patio.
Validate Pergola Information
-
Where is Pergola located?
- LHS
- RHS
- Front
- Rear
- Freestanding Rear
- Freestanding Front
-
Confirm pergola type and size is as per spreadsheet
-
Scope of Work - Site measure. Upload site plan sketch
Variations
Electrical
-
LIGHTING DEFINITION: Only rear patio replacement to have lighting installed [adequate = 1 batten for small areas, 2 for larger areas.]
-
Is there lighting installed under patio structure? Take Photo of location of lighting. How many lights are installed?
-
Take photo of completed installation
-
Does conduit for carport lighting need to be isolated and reinstated?
Variations Other
-
Is there any roof top infrastructure that will interfere with the patio works?
-
What is the impediment?
- Solar HWS
- Solar Power
- Satellite Dish
- Flu
- Vent
- Shade Sail
- other
- Old Solar plumbing
-
If other describe details.
-
House Sheeting - Is there any sheeting requiring replacement?
-
Length of roof sheet/s to be replaced
-
Number of sheets required.
-
Any other items
Builders Ingoing Assessment
-
This page is for the builder to document whatever they require to assist with on the job management.
-
Take photos of external area and make notes as required
-
Take photos of eave lining area adjacent to the worksite prior to commencing
Builders Handover and ITP
Roof Strengthening - Batching
-
Builder must answer all questions and take clear photos showing outcome achieved.
-
Batch number
-
Take photo of eave connections looking down the trusses.
-
Take a photo of the horizonal strap bracing to trusses.
-
Take a photo of the HIP connections
-
Take a photo of any Gallows Bracket connections
-
Take a photo of the truncated & girder truss strengthening and other connections for Batch 4 properties
-
Take photos of RHS to wall plate and to hanging beam connections
-
Take an overview photo of the completed installation before closing roof
-
Take a photo of sisilation before resheeting
-
Take a photo of completed roof sheeting and flashing reinstatement.
Variations - take photos and add description
-
Variation 1
-
Variation 2
-
Variation 3
-
Variation 4
Patio Installation
-
Footing pre-pour [all columns]
-
Is mesh evident in concrete slab? If not provide details of larger footing size and tie-in to slab.
-
Finished hardstand
-
Patio connection details
-
Overall completion photo
Builder Completion
-
Take photos of external area to confirm no damage on completion.
-
Take photos of eave lining area adjacent to works to confirm no damage on completion
-
Record Date and Time of ITP inspection completed.
-
Full Name of Person Completing ITP Inspection
WEL Representitive Review
-
Is Practical completion achieved? Record Actions
-
Record date and time of review completed
-
Name of WEL Representive who has reviewed and completed.
-
PC certificate Issued and actions registered
-
Has Final Completion been achieved. All actions completed, evidence provided and uploaded to Property House Folder in Sharepoint.