Title Page
-
Site location
-
Inspection date
-
Inspected by
-
Project/Programme Reference
- Kitchen
- Bathroom
- WC
- Roofline & RWG
- Doors
- Windows
- Gas heating
- Radiators
- Electric heating
- CCU
- Rewire
-
Contractor and site representive
-
Customer Present
-
Smoke alarms?
- House
- Flat
- Bungalow
- Bedsit
- Hall
- Landing
- Landing 2
- Other
- Living room
- N/A
-
Gas in property and location of boiler?
Works Inspection Details
Kitchen
-
Kitchen Upgrade
-
Start date
-
Finish date
-
Does the property have a utility room? If yes include in questions below & take photos here
-
Has extractor fan and lighting been installed?
-
Has boxing and skirting been fitted?
-
Has the radiator and door been painted?
-
Has a sure stop been installed?
-
Has flooring up to 5 sqm been fitted?
-
Are infills/plinths/kickboards fitted correctly?
-
Are all units, back boards, and end panels, level, free from damage and doors aligned correctly and soft closures fitted?
-
Are all shelves present and fitted correctly?
-
Are drawers fitted correctly and running smoothly?
-
Have splash backs been installed?
-
Is upstand installed correctly?
-
Are worktops, joint and edging strips installed correctly and free from any damage?
-
Are all appliance spaces correct and appliances re-installed correctly?
-
Have cut outs been sealed correctly, service pipe holes the correct size, and copper pipe used?
-
Have isolation valves been fitted and are accessible, including sure-stop where stop tap is located in the kitchen?
-
Has boxing been installed where applicable? If yes note where
-
Has new skirting been fitted?
-
If boiler in kitchen has new C02 alarm been fitted, is in correct position and old one removed?
-
Has a heat detector been fitted (combined with C02 if boiler in kitchen)
-
Has new LED lighting been installed?
-
Are fuse spurs labelled correctly and at least 6 sockets installed?
-
Has an extractor fan been installed?
-
Has vinyl floor been fitted correctly, sealed to the edges and threshold fitted where applicable?
-
Has plastering been carried to standard?
-
Is decoration complete to satisfactory standard?
-
Has kitchen radiator been painted?
-
Have kitchen door been painted?
-
Kitchen - Are there any follow up snags? If yes, note how many
- 0
- 1
- 2
- 3
- 4
- 5
- 6
- 7
Bathroom
-
Bathroom Upgrade
-
Start date
-
Finish date
-
Have the correct bathroom fixtures/fittings been used?
-
Have stickers been removed from fixtures and fittings?
-
Is the bath and bath panel fitted correctly and free from damage?
-
Have the wall boards been installed correctly and sealed correctly?
-
Have the basin and toilet been correctly fitted to the wall?
-
Have shower rails and curtain been installed correctly?
-
Is all silicone sealant installed and to a satisfactory standard?
-
Have isolation valves been fitted and are accessible?
-
Has vinyl floor been fitted correctly, sealed to the edges and threshold fitted where applicable?
-
Has boxing been installed where applicable? If yes note where
-
Has plastering been carried to standard?
-
Is decoration complete to satisfactory standard?
-
Has bathroom radiator been painted?
-
Has bathroom door been painted?
-
Has extractor fan, isolator switch, LED light and pull cord been fitted?
-
Bathroom - Are there any follow up snags? If yes, note how many
- 0
- 1
- 2
- 3
- 4
- 5
- 6
- 7
Additional WC
-
Downstairs/additional WC and WHB Upgrade
-
Start date
-
End date
-
Have the correct bathroom fixtures and fittings been =used ands stickers removed?
-
Have the basin and toilet been correctly fitted to the wall?
-
Has the wall-board for splashback been fitted and sealed correctly?
-
Is all silicone sealant to a satisfactory standard?
-
Have isolation valves been fitted, accessible and copper piping used?
-
Has any boxing been fitted, if so has it been installed to a good standard?
-
Has skirting been fitted, if so has it been installed to a good standard?
-
Has vinyl floor been fitted correctly. sealed to the edges and threshold fitted where applicable?
-
Has plastering been carried to standard?
-
Is decoration complete to satisfactory standard?
-
Has radiator been painted?
-
Has WC door been painted?
-
Has extractor fan, isolator switch been fitted, LED lighting and pull cord installed?
-
DSWC - Are there any follow up snags? If yes, note how many
- 0
- 1
- 2
- 3
- 4
- 5
- 6
- 7
General Site Details and Sign Off
-
Has the site been left clean and tidy?
-
Has all waste been removed?
-
Is scaffolding present?
-
Has customer reported any issues?
-
Overall inspection rating?
-
Places for People Initials
-
Contractor Initials
-
Customer Initials