Title Page
-
Project Title
-
Location
-
Contractor
-
Checked by
-
Conducted on
Plant Commissioning Checklist
Pumping Systems
-
Large Pumps
-
Select large pump
-
Specify
-
Has final system head and pump system curves been received?
-
Has certified performance test data been received?
-
Has certified motor data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer O&M training occurred?
-
Is pump covered by a new or existing on-line training module?
-
Have manufacturer startup and functional tests occurred?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Were factory performance tests witnessed?
-
Were field performance tests witnessed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
Small Pumps with Control Panels
-
Select small pump
- Grit Pump
- RAS/WAS Pump
- Recycle Pump
- Non-potable Water Pump
- Unthickened Sludge Pump
- Groundwater Pumps
- Other
-
Specify
-
Has final system head and pump system curves been received?
-
Has certified performance test data been received?
-
Has representative motor data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer O&M training occurred?
-
Is pump covered by a new or existing on-line training module?
-
Have manufacturer startup and functional tests occurred?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Were field performance tests witnessed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Circuits, fuses, switches, terminals, etc. are provided with a legible and durable identification label.
-
No visible damage to impair safety.
-
Work done properly recorded in logbook.
-
An up-to-date schematic diagram displayed.
-
All accessible live parts screened with insulating plate or earthed metal.
-
All exposed conductive parts effectively earthed.
-
Earthing system effectively connected.
-
Warning notice displayed at main bonding connections.
-
All protective devices are functioned properly and correctly set.
-
Suitable interlock scheme provided to prevent parallel operation of two or more sources of supply and 4-pole incoming and interconnecting circuit breakers provided for supply to be taken from more than one source and is interconnected.
-
Electrically and mechanically interlocked 4-pole changeover device(s) where standby generator set(s) is installed.
-
The breaking capacity of all circuit breakers /interconnection devices are able to withstand the prospective fault current.
-
Protective relays have been correctly set and overcurrent protective devices suitably set for all circuits.
-
Protective type current transformers are used for protective relays.
-
A means of isolation provided for every circuit.
-
Operation of circuit breakers and main switches checked.
-
Control, indication and alarm functions checked.
-
No undersized conductor used between the main busbar and fuse/MCB’s.
-
Fuses/MCB’s matching the lowest rated conductor in the circuit.
-
Suitable cable terminations provided.
-
Cable conductors of correct phases connected.
-
Single-pole devices for protection or switching connected in phase conductors only.
Preliminary Treatment Process Equipment
-
Comminutors and Screening Equipment
-
Select comminutors and screening equipment
- Comminutors
- Influent Screens
- Screenings Dewatering Equipment
- Screenings Conveyor
- Other
-
Specify
-
Has final system head and pump system curves been received?
-
Has certified performance test data been received?
-
Has representative motor data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer O&M training occurred?
-
Is pump covered by a new or existing on-line training module?
-
Have manufacturer startup and functional tests occurred?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Were field performance tests witnessed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Has representative equipment and motor performance test data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer startup occurred?
-
Has manufacturer O&M training occurred?
-
Is equipment covered by a new or existing on-line training module?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Have spare parts been received and turned over to Treatment Division?
-
Have electrical and control checks been completed?
-
Has warranty been received?
Grit Removal and Primary Treatment
-
Select equipment
- Grit In-tank Equipment
- Grit Classifier
- Grit Conveying
- Primary Clarifier Collector
- Scum Collection & Management
- Other
-
Specify
-
Has final system head and pump system curves been received?
-
Has certified performance test data been received?
-
Has representative motor data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer O&M training occurred?
-
Is pump covered by a new or existing on-line training module?
-
Have manufacturer startup and functional tests occurred?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Were field performance tests witnessed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Has representative equipment and motor performance test data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer startup occurred?
-
Has manufacturer O&M training occurred?
-
Is equipment covered by a new or existing on-line training module?
-
Have electrical and control checks been completed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
Secondary Treatment Process Eqiupment
-
Secondary Treatment
-
Select secondary treatment equipment
-
Specify
-
Has final system head and pump system curves been received?
-
Has certified performance test data been received?
-
Has representative motor data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer O&M training occurred?
-
Is pump covered by a new or existing on-line training module?
-
Have manufacturer startup and functional tests occurred?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Were field performance tests witnessed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Has representative equipment performance test data been received?
-
Has representative (certified if larger than 250 HP) motor performance test data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer startup and functional tests occurred?
-
Has manufacturer O&M training occurred?
-
Is equipment covered by a new or existing on-line training module?
-
Have electrical and control checks been completed?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Has testing to demonstrate uniform air flow distribution been completed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Have clarifier torque tests been completed?
Disinfection Equipment
-
Select disinfection equipment
- UV Equipment System
- HOCl Storage
- HOCL Pump/meter Equipment
- HOCL Injection Mixing Equipment
- Dechlor Storage
- Dechlor Pump/meter Equipment
- Other
-
Specify
-
Has final system head and pump system curves been received?
-
Has certified performance test data been received?
-
Has representative motor data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer O&M training occurred?
-
Is pump covered by a new or existing on-line training module?
-
Have manufacturer startup and functional tests occurred?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Were field performance tests witnessed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Has representative equipment performance test data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has UV manufacturer inspected the installation?
-
Has contractor/vendor inspected the installation?
-
Has UV manufacturer startup and functional tests occurred?
-
Has contractor/vendor startup and functional tests occurred?
-
Has UV manufacturer O&M training occurred?
-
Has contractor/vendor O&M training occurred?
-
Is equipment covered by a new or existing on-line training module?
-
Have electrical and control checks been completed (see separate checklist)
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Is equipment covered by a new or existing on-line training module?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Has UV level control failure to safe condition been demonstrated?
-
Has chemical handling and storage safety equipment been demonstrated and accepted?
Tertiary Treatment Process Equipment
-
Filtration
-
Select filtration equipment
- Underdrains and Troughs
- Sweeps or Air Grids
- Media
- Air Wash Compressor
- Disk Filters
- Other
-
Specify
-
Has final system head and pump system curves been received?
-
Has certified performance test data been received?
-
Has representative motor data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer O&M training occurred?
-
Is pump covered by a new or existing on-line training module?
-
Have manufacturer startup and functional tests occurred?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Were field performance tests witnessed?
-
Has warranty been received?
-
Have spare parts been received and turned over to Treatment Division?
-
Has representative equipment and motor performance test data been received?
-
Has final approved shop drawings been received?
-
Has final approved O&M manual been received?
-
Has manufacturer inspected the installation?
-
Has manufacturer startup occurred?
-
Has manufacturer O&M training occurred?
-
Is equipment covered by a new or existing on-line training module?
-
Have spare parts been received and turned over to Treatment Division?
-
Has functionality of manufacturer control system been demonstrated?
-
Has vendor control panel/facility SCADA system interface been successfully demonstrated?
-
Have electrical and control checks been completed?
-
Has warranty been received?
Completion
-
Additional Comments
-
Checked by
-
Witnessed by
-
Contractor Name & Signature