Title Page

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

Prior to Rough-in

  • Latest plans on jobsite (note revision #)

  • Has sewer and rough in layout been checked against architectural drawings and hydraulic drawings?

  • Water Test (needs to be turned off)

  • Does Waste Size Piping meet relevant standards and hydraulic engineer's specification?

  • Do materials meet relevant standards and hydraulic engineer's specification?

Rough-In Checklist

  • Water Test (needs to be turned off)

  • Does plumbing work meet minimum slope requirements?

  • Do all pipes,fittings and jointing methods meet relevant standards or hydraulic engineers specifications?

  • Have all clips, saddles, hangers been placed at correct intervals as per relevant standards, hydraulic engineers or manufacturers specification?

  • Have all inspection openings, expansion joints been placed at correct intervals? <br>

  • Have all waste points, lugged elbows, mixers,in wall cisterns and support noggins been placed at correct heights and depths?

  • Have all cold,hot,hot return, rainwater lines, hot water locations and solar panel locations been ran as per hydraulic engineers drawings?

  • Have all vents been brought through ceiling or roof?

  • Have all leak control flanges been installed?

  • Have all pipes been lagged according to relevant standards or hydraulic engineers specifications?

  • Have all pipes penetrating through fire rated walls, had fire collars or fire caulking placed around them?

  • Have all water lines and sewer drain been tested?

Testing and Final Check

Are the items installed correctly? (Please tick where rectification is required)

Pressure reducing valve

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Fittings

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

PC Items

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Hot water system

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

T/P Toilets

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Backflow requirements

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Mixers/taps

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Basins/sinks/bottle traps/plug and wastes

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Sewage/Drains/Flush

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Stormwater Pits

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Downpipes

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

IO Covers installed

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

Meter connection

  • Correctly installed

  • Correct Item

  • Correct location

  • Working

  • Pressure test

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.