Title Page

  • Gainesville -Powder Line

  • Conducted on

  • Bobby Garrett

  • Gainesville. Ga

Load Side

  • Is the incoming material being inspected for defects?

  • Are the hook instructions for the die being hung pulled up?

  • Are the hook instructions being followed?

  • Are hooks being burnt as prescribed?

  • Is the "Burnt Hook Log" updated?

Washer

  • Are titrations being completed every 2 hours?

  • Stage 1 - Is temp between 130F-140F?

  • Is the PSI between 15-20?

  • Stage 1 - Is the bv% between 1.34% - 1.68%

  • Stage 1 - Is the C titration >1?

  • Stage 1 - Is the dry off oven temperature between 240F -260F?

  • Stage 2 - Is the PSI between 15-20?

  • Stage 2 - Is the conductivity less than 5000 us?

  • Stage 2 - Is the PH between 10-11?

  • Stage 3 - Is the PSI between 15-20?

  • Stage 3 - Is the conductivity less than 1500 us?

  • Stage 3 - Is the PH between 8-10?

  • Stage 4 - Is the PSI between 15-20?

  • Stage 4 - Is the conductivity less than 500 us?

  • Stage 4 - Is the PH between 6-8?

  • Stage 5 - Is the temp between 100F-110F?

  • Stage 5 - Is the PSI between 15-20?

  • Stage 5 - Is the Cr level between 8.0 - 10.0 ML's?

  • Stage 5 - Is the fluoride levels in range for the line speed being ran? (12fpm = 400-600) (18fpm = 600-800)

Paint Kitchen

  • Have paint batches being used been inspected prior to being used?

  • Are all paint batches being climatized before being used?

  • Are all tools in good condition?

  • Is tool calibration up to date?

  • Are reclaim pump pressures within range?

  • Is the temp in the room within range?

  • What is reaction plan if the temp is out of range?

  • Is the compressed air moisture within range?

  • What is reaction plan if the air moisture is out of range?

  • Is the differential pressures with range?

  • What is reaction plan if the pressures are out of range?

  • Are all PM's current?

  • Which PM's are past due date?

Bake Oven

  • Is the oven temp correct for the material being painted?

  • Is the oven being checked every 5 minutes?

  • What is the longest span of time the oven has not been checked?

  • Has the datapaq been ran?

Unload Side / QC

  • Are all QC tools in good condition?

  • Are all tools calibrated?

  • Which tool need calibration?

  • Is the QC Tech performing the tests per ASTM?

  • Are the parts being packaged per the AS400 and die draw?

  • Do the AS400 and die draw instruction match?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.