Information
-
Apartment Number
-
Conducted on
-
Prepared by
Acoustics and Air tightness
-
Has all acoustical caulking been completed?
-
Have windows/Doors and cavity stops been siliconed/foamed or Passive purple?
-
Are all gaps for air leakage filled? Foamed or Caulked
-
Has Passive purple been painted over foam/Wall to ceiling joint?
-
Have all outside penetrations been foamed or caulked ?
-
Is floor membrane folded below plasterboard?
Fire Protection
-
Does plasterboard in hallway go up to ceiling sofit and sealed with fire mastic?
-
Are all wall penetrations in hallway fire stopped with Dampers/fire mastic or foam
-
Are SVP penetrations fire stopped,foamed? Labelled and photographed?
-
Have steel beams been painted with intumescent paint? Labelled and photographed
-
Do all fire rated door lining have intumescent strip installed?
Drywall/Carpentry
-
Are bathroom boxing correct? Is Mirror cut out correct size?
-
Are all door linings/Window boards fitted correctly?
-
Have pattress been completed?
Mechanical
-
IS MVHR ducting installed?
-
Is MVHR ducting insulated where needed?
-
Have all duct penetrations been fire/acoustic caulked?
-
Have ceiling inlets/outlets been installed
Plumbing
-
Is all plumbing complete and tested ? Tests have been witnessed ?
-
Have SVP been insulated/lagged?
-
Has all piping insulation been installed where required?
-
Are services installed correctly?
-
Has boiler been set out and flue drilled?
-
Have boiler/MVHR condense been installed?
Electrical
-
is wiring complete?
-
Are electrical mains installed?
-
Has consumer unit been fitted?
-
have required noggins been installed i.e for ceiling pendants
Electrical supervisor sign off
-
I confirm all works complete and ready for boarding
Plumbing and heating supervisor
-
I confirm all works complete and ready for boarding
Site manager
-
Add signature