Title Page
-
Grovelands Purley
-
Conducted on
-
Prepared by
-
Location
-
Take photo of 2 sample panels (Show location on drawings)
-
Check setting out (reference with drawings)
-
All horizontal and vertical joints aligned and within tolerance
-
Brick slips
-
Brickwork/Blockwork
-
Bedding wall plates
-
Padstones
-
Vertical Fire barrier
-
Horizontal Fire barrier
-
Check structural opening sizes
-
Have cavity closer been installed correctly
-
Have lintels been installed correctly (type and position)
-
Installation of prefabricated lintels
-
Air bricks/ ventilation
-
Install DPC/ cavity trays
-
Weepholes
-
Install wall ties
-
Cavities cleaned
-
Install cavity insulation
-
Install vertical DPC / movement joints
-
Protect facework from damage
-
Mortar mix gauged correctly and colour
-
House keeping
-
Facework cleaned and made good
Signed by
-
Name