Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Works carried out under gas permit number
-
PERMIT NUMBER:
Roughin works complete
-
All Roughing works completed, including risers and Isolation. <br>
-
Reason for works not being completed
-
Type of test
Installation type
-
-
Is installation clearly marked on drawings, "As Built"
-
Yes
-
No
-
Sketch of localised pipe runs or location (if required)
-
Add media
-
Pressure test held for a period of no less than 30 min at at min pressure of 5psi (35 Kpa) as per code. <br>
-
Check all joints and fittings and retest
-
Gauge pressure
-
Start time of test
-
End time of test
-
This will certify that I have tested the piping installed under the above permit with air at a
minimum pressure of 5 p.s.i./ 35 KPa gauge for a minimum of 30 min with no loss of pressure
and that, to my knowledge, all piping, appliances and vents are installed in accordance with the
latest edition of the CAN/CSA Gas Code and have been left in a safe condition. -
Installer / Lead Hand
Customer sign off
-
Add signature