Title Page

  • Crew Leader

  • Neighborhood

  • Address or Lot #

  • Number of Workers

  • Hours on Job Today

  • Conducted on

  • Job Completed?

  • If no, explain why and estimate how much longer the job will take to complete:

Rough-In Checklist

  • 1. Number of boots completed (mastic, insulated properly, and flex run to trunk line or box). Choose N/A if previously completed.

  • Total number of boots

  • Supply

  • 2. Number of flex lines completed – excluding bypass (connected to boots properly, strapped/supported every 4 feet, chases run vertically not pinched and strapped, connected to plenums, boots, boxes, and/or trunklines)

  • Total number of flex lines

  • 3. Number of Trunk Lines Completed (wrapped in duct wrap or foamed, all saddle collars and flex connected) (*this does not include supply from supply plenum, refer to supply plenum connections for that number)

  • Total number of trunk lines

  • 4. Number of Supply Boxes Completed (all start collars correctly connected and flex connected) (*this does not include supply from supply plenum, refer to supply plenum connections for that number)

  • Total number of supply boxes

  • 5. Number of Air handlers/furnaces/mini splits mounted or in place (air handler must have foam blocks and pan, furnace must have pan and bricks, mini split must be mounted ~ if installing during trim out, make note below and include any materials required)

  • Number of Air Handlers Completed

  • Total number of Air Handlers

  • Number of Furnaces Completed

  • Total number of Furnaces

  • Number or Mini Splits Completed

  • Total number of Mini Splits

  • 6. Supply Plenum and Return plenum connected (screwed correctly on all sides, taped and ready for mastic). Plenums must be supported with two point of contact. ~ if there is a stand and a return plenum will not be used add to notes below

  • Number of Supply Plenums Completed

  • Total Number of Supply Plenums

  • Number of Return Plenums Completed

  • Total number of Return Plenums

  • 7. *Supply and return connections hooked into plenums (includes dampers and all supply boxes/trunklines) **bypass is included in next question

  • Total number of Supply and Return Connections

  • 8. **Bypass installed for zoned system (proper length for a bypass, try to use a full length of flex) Installed

  • Total number of Bypasses

  • 9. Return boxes installed (framed on at least 3 sides, mastic, and connected to flex)

  • Total number of Return Boxes

  • 10. Mastic all Boots, plenums, return boxes, connections to floor, and supply boxes (Choose One)

  • If no, explain why

  • 11. Line sets completed (check for cuts in insulation, taped every 5ft, strapped every 4 ft, T-stat wire also attached)

  • Total number of Line Sets

  • 12. Drain line completed (armor flex installed on horizontal pipe, pipe has slope on horizontal sections, strapped every 4ft, primed and glued – be sure that inspector can see it) (Choose One)

  • If no, explain why

  • 13.T-Stat Run to proper location (set to 60” from the floor, stapled to secure, ran to unit or location of zone board)

  • Total number of T-Stat Run

  • 14. Bath fans installed (placed as close as possible to mechanical plan, flex run to outside, dampers installed)

  • Total number of Bath Fans

  • 15. Dryer vent installed (no more than 35ft long – write number on box, strapped with metal strapping at elbows and every 4ft, run out of box vertically if possible, taped) (Choose One)

  • If no, explain why

  • 16. Microwave/range hood pipe installed (taped and supported every 4ft with metal straps) (Choose One)

  • Size of Pipe

  • If no, explain why

  • 17. Gas lines installed (lines are run to all locations based on mechanical plan, lines are glued and capped where needed, manifold is accessible location, all lines are labeled) (Choose One)

  • If no, explain why

  • 18. Fire Foam every opening (all vents from bath fans, dryer and microwave; all chases, flex or pipe between floors, gas lines, and thermostat wires) (Choose One)

  • If no, explain why

Items Needed For Trim-Out

  • Size of Returns Installed (Include amount of each):

  • Size of boots installed (include amount of each):

  • Other:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.